1. Updated trade license, Tax certificate, BIN, Electrical contractor with ABC Licence
2. The tenderer shall have general working experience of at least 3 (three) years.
3. A satisfactory completion of similar works of at least Tk 3.0 lac under 1 number of contract(s) over a period of 5 years shall be required.
4.The required average annual construction turnover shall be greater than Tk 5.0 lac in best of 2 years over the last 5 years.
5.The minimum amount of liquid asset or working capital or credites facilities of the tenderer shall have tk 3.0 lac.
6.The work shall have to be completed by 60 days.
7. As per TDS, PCC
Replacement works of 02 (two) set Circuit Breaker & 01 (one) set CT at Pabna Grid Sub-station under GMD, Power Grid, Ishwardi.