1. Valid updated trade license, Tax Certificate, BIN.
2. A satisfactory completion of similar works, i.e civil construction/maintenance works of at least Tk 1.0 lac under one number of contract over a period of 5 years shall be required.
3. The required average annual construction turnover shall be greater than Tk 2 lac in best of 2 years over the last 5 years.
4. The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 1.0 lac.
5. As per TDS and PCC
Painting of control room & security post at Pabna Grid Sub-Station under GMD, Power Grid, Ishwardi.