The Tenderer must have successfully completed at least one (1) Solar PV Hybrid Power System project with Netmetering within the last three (03) years, each with a minimum capacity of 35 kW and incorporating Lithium-ion Battery Energy Storage System (BESS). This project must have been completed, commissioned and remained operational by bidder. Documentary evidence, such as Completion Certificate/Performance Certificate issued by the Client/Procuring Entity, shall be submitted along with the Tender and others eligibility specified in TDS
Supply and installation of Solar System with High-voltage Lithium Iron Phosphate (LiFePO4) Battery in BIAM Foundation, Regional Center, Bogura