ABC Category Electrical Supervisory License from Bangladesh Electrical Licensing Board
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor shall be [03] years. Years counting backward from the date of publication of IFT in the newspaper.
The minimum specific experience as a Prime Contractor in construction works under public sector of at least [01] contract(s) of minimum 10.0 kWp or higher capacity on-Grid installation testing commissioning successfully completed within the last [03] years, each with a value of at least Tk. [5 Lakh] in Power Grid/ DESCO/DPDC/BPDB or or any other Government Electricity Company/Institution. Years counting backward from the date of publication of IFT in the newspaper.
Others in as per TDS.
Supply, Installation, Testing and Commissioning work of 10.0 kWp capacity on-Grid Solar System with Net Metering at GMD Rangamati Office under GMD, Rangamati, Power Grid