View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | - |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As described in ITT Clause and TDS. |
As described in ITT Clause and TDS. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk 18,49,000.000 ( Eighteen lac Forty Nine Thousand) Per Year over the last 05 (five) years. The years counting backward from the date of publication of IFT in the newspaper.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper] The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk .13,87,000.00 ( Thirteen lac Eighty Seven Thousand )
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment. |
The required average annual construction turnover shall be greater than Tk 1,10,96,000.000 ( One Crore Ten lac Ninety Six Thousand) Per Year over the last 05 (five) years. The years counting backward from the date of publication of IFT in the newspaper.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper] The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk .13,87,000.00 ( Thirteen lac Eighty Seven Thousand )
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment. |
| TDS/PDS--C. Qualification Criteria-- |
|
|
| Brief Description of Goods,Works or Service | 1. Construction of Head Teacher's room with attached toilet of KESHOBPUR Primary School under PEDP4 (Vertical-1Room+Stair ) Package No: e-Tender/PEDP4/JSR/KES/2024-25/W15A.01500 2. Construction of Head Teacher's room with attached toilet of SAT BARAIA Primary School under PEDP4 (Vertical-1Room+Stair) Package No: e-Tender/PEDP4/JSR/KES/2024-25/W15A.01500 |
1. Construction of Head Teacher's room with attached toilet of KESHOBPUR Primary School under PEDP4 (Vertical-1Room+Stair ) Package No: e-Tender/PEDP4/JSR/KES/2024-25/W15A.01500 2. Construction of Head Teacher's room with attached toilet of SAT BARAIA Primary School under PEDP4 (Vertical-1Room+Stair) Package No: e-Tender/PEDP4/JSR/KES/2024-25/W15A.01500 |