Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | BOQ correction. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 27/11/2024 12:00 | 02/12/2024 12:00 |
| Opening Date & Time | 27/11/2024 14:00 | 02/12/2024 14:00 |
| Last date & time for Tender/Proposal Security Submission | 27/11/2024 13:00 | 02/12/2024 13:00 |
| Closing Date & Time | 27/11/2024 14:00 | 02/12/2024 14:00 |
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its Tender the following additional documents: (a) The Tender Submission Letter (Form e-PW3-1) as furnished in Section 5: e-Tender Forms;
(b) Tenderer Information (Form e-PW3-2) as furnished in Section 5: e-Tender Forms;
(c) The priced Bill of Quantities for each lot in accordance with ITT Clauses 26 and 27;
(d) Tender Security as stated under ITT Clauses 34 and 35. (e) Written confirmation authorizing the signatory of the Tenderer including National ID to submit the e-Tender, as stated under ITT Sub Clause 39.4; (f) Valid Trade license to be mapped from e-GP Common document library of the Tenderer ; (g) Documentary evidence of Tax Identification Number (TIN) and Value Added Tax (VAT) as a proof of taxation obligations as stated under ITT Sub Clause 5.10 to be mapped from e-GP Common document library of the Tenderer; (h) Technical Proposal describing work plan & method, personnel, equipment and schedules as stated under ITT Clause 30; (i) documentary evidence as stated under ITT Clause 28 and 31 establishing the Tenderer’s eligibility and the minimum qualifications of the Tenderer required to be met for due performance of the Works and physical services under the Contract; (j) Documents establishing legal and financial autonomy and compliance with commercial law, as stated under ITT Sub-clause 5.4 in case of government owned entity; (k) Tenderer’s Past Performance Information to be provided in ‘ Tenderer's Past Performance Information e-PW3 – 5 (A) and 5(B) ’ ; and
For Sub station-Generator: 1. Up to date "ABC" catagory contractor & Supervisory license from electricity licencing Board of Bangladesh. 2. Complete Site visit report duly authenticated by Engineer-in-Charge; not below the rank of AE of PE office. 3. List of electrical equipment in Bidder's official pad mentioning the IFT reference
4. Manufacturer Authorization Letters mentioning Model No. [Substation 5. Warranty Certificate issued by the Manufacturer [Substation equipments,Generator]
6. Spare Parts Supplying Assurance Certificate Issued by the Manufacturer.[Substation
7. After Sales Service Assurance Certificate issued by the Manufacturer/ Tenderer for proposed
8. Valid ISO-9001Certificate of the Sub-station Manufacturer or evidence that the 9. Technical proposal issued by the manufacturing company, duly sealed and signed by the bidder. 10. Catalog/ brochure of proposed items mentioning brand and country of origin.
11. Type Test Certificate for the proposed brand of 11 KV HT Panel with LBS, Transformer, PFI 12. Type Test Certificate for XLPE cable and NYY Cable.
13. Country of origin declaration for Generator [concern chamber of commerce certificate of the 14. Tenderer shall submit an assurance certificate declaring explicitly to perform the job within time duly. (Bar chart or gantt chart)
For lift 1
2. Before submitting Lift installation drawing the Lift company must visit the site to ensure Door
3. All electrical and civil works mending good the damages in connection with installation of the lift
4. The bidder shall submit the technical proposal with sealed & signed by manufacturing company
5. The bidder shall submit a certificate by manufacturing company stated that minimum 200 Nos. 6. The main parts of the proposed lift such as motor, gear box/gearless, controller, cabin, door and door drive system must follow the actual drawing, design of the lift manufacturing country and the logo/name of the manufacturing country must be embedded with the body of the proposed lift.
7. Country of origin declaration for Lift A certificate must be submitted which stated that the other parts of the proposed lift are made
8. The block diagram of the complete lift system including all control system with ACVVVF, power
9. The bidder shall submit the detail address of the factory, telephone no., website address, email 10. Before shipment, Factory Acceptance Test (performance test of safety devices of lift and
Quality assurance tests of the products as per standards) shall have to be carried out by the
11. Post landing inspection for imported lift(s) shall be done by representatives (nominated two personal) of Procuring Entity
(l) any other document as specified in the TDS. |
The Tenderer shall submit with its Tender the following additional documents: (a) The Tender Submission Letter (Form e-PW3-1) as furnished in Section 5: e-Tender Forms;
(b) Tenderer Information (Form e-PW3-2) as furnished in Section 5: e-Tender Forms;
(c) The priced Bill of Quantities for each lot in accordance with ITT Clauses 26 and 27;
(d) Tender Security as stated under ITT Clauses 34 and 35. (e) Written confirmation authorizing the signatory of the Tenderer including National ID to submit the e-Tender, as stated under ITT Sub Clause 39.4; (f) Valid Trade license to be mapped from e-GP Common document library of the Tenderer ; (g) Documentary evidence of Tax Identification Number (TIN) and Value Added Tax (VAT) as a proof of taxation obligations as stated under ITT Sub Clause 5.10 to be mapped from e-GP Common document library of the Tenderer; (h) Technical Proposal describing work plan & method, personnel, equipment and schedules as stated under ITT Clause 30; (i) documentary evidence as stated under ITT Clause 28 and 31 establishing the Tenderer’s eligibility and the minimum qualifications of the Tenderer required to be met for due performance of the Works and physical services under the Contract; (j) Documents establishing legal and financial autonomy and compliance with commercial law, as stated under ITT Sub-clause 5.4 in case of government owned entity; (k) Tenderer’s Past Performance Information to be provided in ‘ Tenderer's Past Performance Information e-PW3 – 5 (A) and 5(B) ’ ; and
For Sub station-Generator: 1. Up to date "ABC" catagory contractor & Supervisory license from electricity licencing Board of Bangladesh. 2. Complete Site visit report to avoid any alternation of the structure. 3. List of electrical equipment in Bidder's official pad mentioning the IFT reference
4. Manufacturer Authorization Letters mentioning Model No. [Substation 5. Warranty Certificate issued by the Manufacturer [Substation equipments,Generator]
6. Spare Parts Supplying Assurance Certificate Issued by the Manufacturer.[Substation
7. After Sales Service Assurance Certificate issued by the Manufacturer/ Tenderer for proposed
8. Valid ISO-9001Certificate of the Sub-station Manufacturer or evidence that the 9. Technical proposal issued by the manufacturing company, duly sealed and signed by the bidder. 10. Catalog/ brochure of proposed items mentioning brand and country of origin.
11. Type Test Certificate for the proposed brand of 11 KV HT Panel with LBS, Transformer, PFI 12. Type Test Certificate for XLPE cable and NYY Cable.
13. Country of origin declaration for Generator [concern chamber of commerce certificate of the 14. Tenderer shall submit an assurance certificate declaring explicitly to perform the job within time duly. (Bar chart or gantt chart)
For lift 1
2. Before submitting Lift installation drawing the Lift company must visit the site to ensure Door
3. All electrical and civil works mending good the damages in connection with installation of the lift
4. The bidder shall submit the technical proposal with sealed & signed by manufacturing company
5. The bidder shall submit a certificate by manufacturing company stated that minimum 200 Nos. 6. The main parts of the proposed lift such as motor, gear box/gearless, controller, cabin, door and door drive system must follow the actual drawing, design of the lift manufacturing country and the logo/name of the manufacturing country must be embedded with the body of the proposed lift.
7. Country of origin declaration for Lift A certificate must be submitted which stated that the other parts of the proposed lift are made
8. The block diagram of the complete lift system including all control system with ACVVVF, power
9. The bidder shall submit the detail address of the factory, telephone no., website address, email 10. Before shipment, Factory Acceptance Test (performance test of safety devices of lift and
Quality assurance tests of the products as per standards) shall have to be carried out by the
11. Post landing inspection for imported lift(s) shall be done by representatives (nominated two personal) of Procuring Entity
(l) any other document as specified in the TDS. |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | TDS correction. |
| Field Name | Old Value | New Value |
|---|---|---|
| TDS/PDS--C. Qualification Criteria-- | (a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 07 (Seven) years.
(b) The minimum specific experience as a Prime Contractor in construction works of at least Single of contract of similar nature (installation and testing commissioning of Lift, Electrical Substation, Generator, Home solar and related civil works in a single package), complexity and methods/construction technology successfully completed within the last 05 (Five) years, each with a value of at least Tk.22 (twenty two) crore. |
(a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 07 (Seven) years.
(b) The minimum specific experience as a Prime Contractor in construction works of at least Single of contract of similar nature (installation and testing commissioning of Lift, Electrical Substation and related Electrical & civil works in a single package), complexity and methods/construction technology successfully completed within the last 05 (Five) years with a value of at least Tk.22 (twenty two) crore. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Some changes in documents has done. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As per TDS. |
As per TDS. |
| TDS/PDS--C. Qualification Criteria-- | (a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 07 (Seven) years.
(b) The minimum specific experience as a Prime Contractor in construction works of at least Single of contract of similar nature (installation and testing commissioning, minimum 5 nos of 1000kg capacity Lift, minimum 1 no of 1250 KVA capacity Electrical Substation, minimum 1 no of 400KVA capacity Generator, Deep tubewell, Home solar and related civil works in a single package), complexity and methods/construction technology successfully completed within the last 03 (three) years, each with a value of at least Tk.27 (twenty seven) crore. |
(a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 07 (Seven) years.
(b) The minimum specific experience as a Prime Contractor in construction works of at least Single of contract of similar nature (installation and testing commissioning of Lift, Electrical Substation, Generator, Home solar and related civil works in a single package), complexity and methods/construction technology successfully completed within the last 05 (Five) years, each with a value of at least Tk.22 (twenty two) crore. |
| Brief Description of Goods,Works or Service | Supply and Installation of Electrical Sub-station, Generator, Lift external electrification, Solar system, Substation, Generator & Pump house construction and other Electrical Works under Gabtoli city Palli Project. (package-W-06) |
Supply and Installation of Electrical Sub-station, Generator, Lift external electrification, Solar system, Substation, Generator & Pump house construction and other Electrical Works under Gabtoli city Palli Project. (package-W-06) |