i) As Per Tender Document.
ii) The Tenderer whose total quoted amount above/below the 10% (Ten percent) of official estimated cost (Tenderer must upload Rate Analysis supporting the quoted amount) shall be considered as rejected.
iii) 60(Sixty) days after last issuance of departmental materials.
iv) The Tenderer should have the similar work experience certificate in the CHT. Hilly Areas.
Cutting of trees on both sides of 33KV Takurchar to Dighinala, Dighinala to Longedu source line, Cutting of trees on both sides of different 11KV feeders of 33/11 KV Dighinala & 33/11KV Longedu Substation and also Dismantling/Remove, Recovery, Installation and replacement works of 11/0.4KV distribution transformers due to burnt/overload at all 11KV Feeders of Dighinala ESU under Distribution Division-Khagrachari, BPDB, Khagrachari.