Amendment / Corrigendum No. : 5
|
|
| Amendment / Corrigendum Text : | Due to some unavoidable issues opening date is needed to be extended. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 20/07/2025 | 31/07/2025 |
| Document last selling date & time | 30/06/2025 10:30 | 07/07/2025 10:30 |
| Opening Date & Time | 30/06/2025 12:30 | 07/07/2025 12:30 |
| Last date & time for Tender/Proposal Security Submission | 30/06/2025 11:45 | 07/07/2025 11:45 |
| Start Date(Lot No : 1) | 06/07/2025 | 10/07/2025 |
| Closing Date & Time | 30/06/2025 12:30 | 07/07/2025 12:30 |
|
Amendment / Corrigendum No. : 4
|
|
| Amendment / Corrigendum Text : | Due to the modified demand of Parliament Authority BOQ is to be corrected. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 30/06/2025 | 20/07/2025 |
| Document last selling date & time | 26/06/2025 10:30 | 30/06/2025 10:30 |
| Opening Date & Time | 26/06/2025 12:30 | 30/06/2025 12:30 |
| Last date & time for Tender/Proposal Security Submission | 26/06/2025 11:45 | 30/06/2025 11:45 |
| Start Date(Lot No : 1) | 29/06/2025 | 06/07/2025 |
| Closing Date & Time | 26/06/2025 12:30 | 30/06/2025 12:30 |
| Brief Description of Goods,Works or Service |
|
|
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | Due to some unavoidable issues last security submission date and opening date should be ammended. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 25/06/2025 | 30/06/2025 |
| Document last selling date & time | 17/06/2025 10:30 | 26/06/2025 10:30 |
| Opening Date & Time | 17/06/2025 12:30 | 26/06/2025 12:30 |
| Last date & time for Tender/Proposal Security Submission | 17/06/2025 11:45 | 26/06/2025 11:45 |
| Start Date(Lot No : 1) | 19/06/2025 | 29/06/2025 |
| Closing Date & Time | 17/06/2025 12:30 | 26/06/2025 12:30 |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Due to the change of the volume of work. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 19/06/2025 | 25/06/2025 |
| Document last selling date & time | 01/06/2025 10:45 | 17/06/2025 10:30 |
| Opening Date & Time | 01/06/2025 12:45 | 17/06/2025 12:30 |
| Last date & time for Tender/Proposal Security Submission | 01/06/2025 11:45 | 17/06/2025 11:45 |
| Start Date(Lot No : 1) | 04/06/2025 | 19/06/2025 |
| Closing Date & Time | 01/06/2025 12:45 | 17/06/2025 12:30 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Official Cost Estimate should be corrected due to the demand of owner agency and further scrutinity by the Higher Authority / Approving Authority. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As per TDS & PCC |
As per TDS & PCC |
| TDS/PDS--C. Qualification Criteria-- |
|
|
| TDS/PDS--C. Qualification Criteria-- |
|
|
| TDS/PDS--C. Qualification Criteria-- |
The minimum capacity is BDT TK 77 lacs |
The minimum capacity is BDT TK 74 lacs |
| TDS/PDS--C. Qualification Criteria-- |
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 (one) contract of similar nature of works, (Wooden & Steel furniture) i.e. any Wooden & Steel furniture manufacture successfully completed within the last 05 years with a value of at least BDT Tk 73 Lacs of Government/ Semi-Government/ Autonomous Bodies in Bangladesh. i.e. years counting backward from the date of publication of IFT in the e-GP System. The above experience/ work completion certificate shall have to be submitted as follows:
i In case of the work done under PWD, the certifying and authenticating authority shall be the concerned Executive Engineer. iii Experience Certificate approved through e-GP system will be preferred. |
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 (one) contract of similar nature of works, (Wooden & Steel furniture) i.e. any Wooden & Steel furniture manufacture successfully completed within the last 05 years with a value of at least BDT Tk 70 Lacs of Government/ Semi-Government/ Autonomous Bodies in Bangladesh. i.e. years counting backward from the date of publication of IFT in the e-GP System. The above experience/ work completion certificate shall have to be submitted as follows:
i In case of the work done under PWD, the certifying and authenticating authority shall be the concerned Executive Engineer. iii Experience Certificate approved through e-GP system will be preferred. |
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents:
(a). The minimum number of years of general experience of the Tenderer to manufacture wooden and steel furniture works shall be minimum Five (05) years.
(b). The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in procurement/construction of works of at least 01 (one) contract of similar nature of works, (Wooden & Steel furniture) i.e. any Wooden & Steel furniture manufacture successfully completed within the last 05 years with a value of at least BDT Tk 73 Lacs of Government/ Semi-Government/ Autonomous Bodies in Bangladesh. i.e. years counting backward from the date of publication of IFT in the e-GP System. The above experience/ work completion certificate shall have to be submitted as follows: iii Experience Certificate approved through e-GP system will be preferred.
(c). The Tenderer shall have minimum amount of liquid assets BDT Tk 68.00 lacs i.e. working capital or credit line(s), net of other contractual commitments at the time of Tender submission with the standard format of CPTU (PW2a-3) (h) Tenderer shall submit an assurance certificate declaring explicitly to perform the job within time duly. (i).Tenderer is expected to be the Member for Bangladesh Furniture Industries Owners Association (j) Rule 27(2) of PPR/2008 will be applied in case of front loading (k) Tenderer shall submit an assurance certificate declaring manufacture/ supply of qualified products. Otherwise the products to be rejected and all rejected products replacing with new demanded products by the required authority. l) Minimum supply/ production capacity (in any govt. organization/semi govt/ autonomous body/ Private Organization) of minimum 5 sets of furniture (wooden/ steel) supply/ manufacture by 5 Years, in a minimum amount of BDT TK 365 lacs, years counting backward from the date of publication of IFT. (Certificate of the minimum supply capacity shall be on the basis of Acceptance Certificate and Certificate of the minimum production capacity from manufacturer is allowable only.)
m) Confirmation Certificate of Warranty Period for at least One (1) year from the manufacturing company is mandatory q) The duration of working time may be extended; if the project time delayed. So that site handed over to be depended on it. r) Products will be taken care of by the contractor until authority would receive finally till the end of project (as per situation). s) No performance guarantee and retention money/ security money won't clear until authority would receive the products. t)All other required qualifications, special terms & conditions of the tender are shown in the ITT, GCC & Tender Data Sheet (TDS), Tender Documents, and PCC. u)Before submission of tender documents , selected list of required furniture repairing process must be physically delivered to Office of the Sub Divisional Engineer, PWD E/M Wood Workshop Sub Division, Mirpur, Dhaka. |
Tenderer shall submit with its Tender, the following additional documents:
(a). The minimum number of years of general experience of the Tenderer to manufacture wooden and steel furniture works shall be minimum Five (05) years.
(b). The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in procurement/construction of works of at least 01 (one) contract of similar nature of works, (Wooden & Steel furniture) i.e. any Wooden & Steel furniture manufacture successfully completed within the last 05 years with a value of at least BDT Tk 70 Lacs of Government/ Semi-Government/ Autonomous Bodies in Bangladesh. i.e. years counting backward from the date of publication of IFT in the e-GP System. The above experience/ work completion certificate shall have to be submitted as follows: iii Experience Certificate approved through e-GP system will be preferred.
(c). The Tenderer shall have minimum amount of liquid assets BDT Tk 65 lacs i.e. working capital or credit line(s), net of other contractual commitments at the time of Tender submission with the standard format of CPTU (PW2a-3) (h) Tenderer shall submit an assurance certificate declaring explicitly to perform the job within time duly. (i).Tenderer is expected to be the Member for Bangladesh Furniture Industries Owners Association (j) Rule 27(2) of PPR/2008 will be applied in case of front loading (k) Tenderer shall submit an assurance certificate declaring manufacture/ supply of qualified products. Otherwise the products to be rejected and all rejected products replacing with new demanded products by the required authority. l) Minimum supply/ production capacity (in any govt. organization/semi govt/ autonomous body/ Private Organization) of minimum 5 sets of furniture (wooden/ steel) supply/ manufacture by 5 Years, in a minimum amount of BDT TK 350 lacs, years counting backward from the date of publication of IFT. (Certificate of the minimum supply capacity shall be on the basis of Acceptance Certificate and Certificate of the minimum production capacity from manufacturer is allowable only.)
m) Confirmation Certificate of Warranty Period for at least One (1) year from the manufacturing company is mandatory q) The duration of working time may be extended; if the project time delayed. So that site handed over to be depended on it. r) Products will be taken care of by the contractor until authority would receive finally till the end of project (as per situation). s) No performance guarantee and retention money/ security money won't clear until authority would receive the products. t)All other required qualifications, special terms & conditions of the tender are shown in the ITT, GCC & Tender Data Sheet (TDS), Tender Documents, and PCC. u)Before submission of tender documents , selected list of required furniture repairing process must be physically delivered to Office of the Sub Divisional Engineer, PWD E/M Wood Workshop Sub Division, Mirpur, Dhaka. |
| Brief Description of Goods,Works or Service |
|
|
| Tender/Proposal Security (Amount in BDT)(Lot No : 1) | 245000.0 | 235000 |