Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Corrigendum for Document/Notice |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 23/09/2025 13:27 | 28/09/2025 13:27 |
| Eligibility of Consultant | as per TDS |
as per TDS |
| Opening Date & Time | 23/09/2025 14:27 | 28/09/2025 14:27 |
| Last date & time for Tender/Proposal Security Submission | 23/09/2025 14:10 | 28/09/2025 14:10 |
| Closing Date & Time | 23/09/2025 14:27 | 28/09/2025 14:27 |
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 years.
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 05 years, each with a value of at least Tk. 5 crore [ |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 years.
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in Construction works of Test TW, Production TW, RCC OHT,AIRU Vessel Type, Pipe Line and House Connection with Minimum 1 year Operation and Maintenance in same package, successfully completed in 01(One) contract within the last 5 years of value at least Tk 650.00 lakh. Years counting backward from the date of publication of IFT. Experience certificates must be uploaded on the official CMS formate of the concerned institution. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk 4 crore 70 lac over the last 3 years.
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 1 crore
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The required average annual construction turnover shall be greater than Tk 500 lac over the last 5 years.
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 300 lac |
| TDS/PDS--C. Qualification Criteria-- | The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works: none |
The Nominated Subcontractor(s) named M/S MOHIBUL INTERNATIONAL Prop. KAZI MD RAKIBUL ISLAM, Narayanganj shall execute the following specific components of the proposed Works: Test Tw, production TW and operation & maintenance of the scheme |
| Brief Description of Goods,Works or Service | piped water supply scheme with 02 nos Test Tubewell, 02 nos Production well, 01 nos Pump House, 01 Nos R.C.C Over Head Water Tank, Mechanical works, Electrical Works, Pipe Line/water distribution Networks, 01 Nos Arsenic and Iron Removal Plant (Capacity:25 m3/hr) etc. under Safe Water Supply Through Out The Country Project. in Rupganj ( site might be changed) |
piped water supply scheme with Test Tubewell, 06 nos Production well, 03 nos Pump House, 03 Nos R.C.C Over Head Water Tank, including necessary Mechanical works, Electrical Works, Pipe Line/water distribution Networks, 03 Nos Arsenic and Iron Removal Plant (Capacity:25 m3/hr) etc. under Safe Water Supply Through Out The Country Project. in Rupganj ( site might be changed) |