View IFT /PQ / REOI / RFP / PPS Notice Details
Amendment / Corrigendum Detail
|
Amendment / Corrigendum No. : 1
|
| Amendment / Corrigendum Text : |
Amendment/ Corrigendum : 01 |
| Field Name |
Old Value |
New Value |
| Document last selling date & time
|
19/11/2025 17:00 |
23/11/2025 17:00 |
| Eligibility of Consultant
|
• All the e-gp enlisted contractor satisfying the criteria mentioned in e-PW2 document attached herewith as per latest PPR-2025 can participate in the tender.
• Payments for work will be made only when the budget is available and funds are released. No additional claims or interest due to payment delays will be considered. R/A bills will be processed based on budget availability and fund allocation. However, work progress will continue unaffected by any delays in fund release or R/A bill processing.
• Latest Technical specification for civil work of BWDB will govern provided in particular specifications.
• The design may be changed/altered/revised (if required) and quantity of tender item may be increased or decreased.
• Prework & Post work will be taken by Taskforce and BWDB’s concern engineer in charge. Final Payment will be made on the measurement taken by Taskforce.
• The selected contractor will handover total work site at a time. No scope to handover the site partly.
• All the conditions are specified in separate sheet attached in General specifications Taskforce guideline of BWDB will govern enclosed in General specifications
**** Payment will be made based on the quantity of pipes actually removed and subject to budget allocation. However, if pipe removal under any package is not possible due to local complications, payment for that package will not be made and It will be declared as completed work.
|
• All the e-gp enlisted contractor satisfying the criteria mentioned in e-PW2 document attached herewith as per latest PPR-2025 can participate in the tender.
• Payments for work will be made only when the budget is available and funds are released. No additional claims or interest due to payment delays will be considered. R/A bills will be processed based on budget availability and fund allocation. However, work progress will continue unaffected by any delays in fund release or R/A bill processing.
• Latest Technical specification for civil work of BWDB will govern provided in particular specifications.
• The design may be changed/altered/revised (if required) and quantity of tender item may be increased or decreased.
• Prework & Post work will be taken by Taskforce and BWDB’s concern engineer in charge. Final Payment will be made on the measurement taken by Taskforce.
• The selected contractor will handover total work site at a time. No scope to handover the site partly.
• All the conditions are specified in separate sheet attached in General specifications Taskforce guideline of BWDB will govern enclosed in General specifications
**** Payment will be made based on the quantity of pipes actually removed and subject to budget allocation. However, if pipe removal under any package is not possible due to local complications, payment for that package will not be made and It will be declared as completed work.
|
| Opening Date & Time
|
20/11/2025 13:00 |
24/11/2025 13:00 |
| Last date & time for Tender/Proposal Security Submission
|
20/11/2025 12:00 |
24/11/2025 12:00 |
| Closing Date & Time
|
20/11/2025 13:00 |
24/11/2025 13:00 |
| Brief Description of Goods,Works or Service
|
NDR Sat1/P-05/2025-26
Removal of 40 nos. illegal Pipe/Boxkols in between Ch. Km 116.000 to Ch. Km 131.140 installed through embankment and repair accordingly in Polder no- 5 & Ch. Km 0.000 to Ch. Km 29.500 installed through embankment and repair accordingly in Polder no- 15 of Satkhira district under Satkhira WD Division-1.
|
NDR Sat1/P-05/2025-26
Removal of 40 nos. illegal Pipe/Boxkols in between Ch. Km 116.000 to Ch. Km 131.140 installed through embankment and repair accordingly in Polder no- 5 & Ch. Km 0.000 to Ch. Km 29.500 installed through embankment and repair accordingly in Polder no- 15 of Satkhira district under Satkhira WD Division-1.
|