Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Due to server related issue Tender Notice has been changed but all other terms & conditions of schedule has been unchanged. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 08/02/2026 17:00 | 15/02/2026 17:00 |
| Opening Date & Time | 09/02/2026 12:00 | 16/02/2026 12:00 |
| Last date & time for Tender/Proposal Security Submission | 09/02/2026 11:00 | 16/02/2026 11:00 |
| Closing Date & Time | 09/02/2026 12:00 | 16/02/2026 12:00 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | 14.1 (a) Clause Required Annual Construction Turn Over has been changed but all other criteria of schedule has been unchanged. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As per stated TDS. |
As per stated TDS. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover under public sector shall be greater than Tk 12.00 Lac over the last 5 financial years. In calculating the annual construction turnover the payment certificate of construction work shall only be considered. Tenderers must submit the payment certificate of construction work for calculating Annual Construction Turnover.
Note 1: Average Annual Construction Turnover will be calculated on the basis of Payment Certificates issued by respective authority.
Note 4: Only the payment certificate of Public Sector Construction Works shall be considered. |
The required average annual construction turnover under public sector shall be greater than Tk 3.00 Lac over the last 5 financial years. In calculating the annual construction turnover the payment certificate of construction work shall only be considered. Tenderers must submit the payment certificate of construction work for calculating Annual Construction Turnover.
Note 1: Average Annual Construction Turnover will be calculated on the basis of Payment Certificates issued by respective authority.
Note 4: Only the payment certificate of Public Sector Construction Works shall be considered. |
| Brief Description of Goods,Works or Service | Different Repair work at Ramgonj Road Sub-Division Office under Lakshmipur Road Division during the year 2025-2026. |
Different Repair work at Ramgonj Road Sub-Division Office under Lakshmipur Road Division during the year 2025-2026. |