The minimum number of years of general experience of the tenderer in the works shall be 5 (five) years. (Years counting backward from the date of publication of IFT in the e-GP System)
The minimum specific electro-mechanical experience as prime contractor in successfully completed in supply and installation of at least one (1) no of minimum of 1000KVA substation and related works and 20KW solar panel installation and related works of value no less than 260 Lakh BDT in one (01) no of contract in any govt. /semi govt. /autonomous bodies in Bangladesh within last 05(Five) years from the date of publication of this tender. i) In case of the work done under any PWD Division the certifying and authenticating authority shall be the concerned Executive Engineer. ii) In case of the work done under any govt./semi govt./autonomous bodies other than PWD, the certifying authority shall be an officer not below the rank of Executive Engineer of PWD.
The required average annual construction turnover under public sector shall be greater than Tk Tk 250 Lakh BDT over the last 05 years or best 05 years in the last 10 years.
The minimum amount of financial resources as liquid asset or working capital or credit line(s) or specific credit commitment or in any combination of them, of the Tenderers shall be Tk 260 Lakh BDT.
The minimum capacity shall be: Tk 260 Lakh BDT.
Replacing the existing overloaded 500 KVA Sub-Station Equipment by newly Supply, Installation, Testing and Commissioning of 1000 KVA Sub-Station Equipment, Control Breaker, HT and LT Cable at National Institute of Local Government (NILG), Agargaon, Dhaka.