View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Technical Specification and others |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC----- | Responsibility of the Supplier is:
1. As per INCOTERMS-2020 |
Responsibility of the Supplier is:
1. As per incoterms-2020 rules |
| PCC----- | The amount of Liquidated Damages is [insert between 0.03 and 0.05 percent] of the contract value as applicable, per day of delay. Guide to application of GCC Sub Clause 34.1 above [ Liquidated damages are equivalent to an amount to be determined in accordance with the following formulae] T = VxPx n
Where;
Intended Completion Date or extended Intended Completion Date, as applicable. |
The amount of Liquidated Damages is 0.05 percent of the contract value as applicable, per day of delay. Guide to application of GCC Sub Clause 34.1 above [ Liquidated damages are equivalent to an amount to be determined in accordance with the following formulae] T = VxPx n
Where;
Intended Completion Date or extended Intended Completion Date, as applicable. |
| PCC----- | The rules of procedure for arbitration proceedings shall be as follows: (i) Contract with foreign Supplier: GCC 46.3 (b)—Any dispute, controversy or claim arising out of or relating to this Contract, or breach, termination or invalidity thereof, shall be settled by arbitration in accordance with the UNCITRAL Arbitration Rules as at present in force. (ii) Contracts with Supplier national of the Purchaser’s country: In the case of a dispute between the Purchaser and a Supplier who is a national of the Bangladesh, the dispute shall be referred to adjudication or arbitration in accordance with the laws of the Bangladesh i.e. Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force. |
The rules of procedure for arbitration proceedings shall be as follows: (i) Contract with foreign Supplier: GCC 46.3 (b)—Any dispute, controversy or claim arising out of or relating to this Contract, or breach, termination or invalidity thereof, shall be settled by arbitration in accordance with the UNCITRAL Arbitration Rules as at present in force. (ii) Contracts with Supplier national of the Purchaser’s country: In the case of a dispute between the Purchaser and a Supplier who is a national of the Bangladesh, the dispute shall be referred to adjudication or arbitration in accordance with the laws of the Bangladesh i.e. Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force. |
| Amendment / Corrigendum/ Addendum No. : | 1 | ||||
| S. No. | File Name | File Description | File Size (in KB) |
||
|---|---|---|---|---|---|
| 1 | Final Specification and others GR-2621.pdf | Amendment | 963434 | ||