View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Corrigendum issued as required changes in TDS & PCC. |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Document last selling date & time | 18/10/2026 16:30 | 25/10/2026 12:30 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Eligibility of Consultant | As stated in ITT and TDS. |
As stated in ITT and TDS. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Location(Lot No : 1) | Morrelganj Ferry Ghat | Morrelganj Ferry Ghat, Bagerhat | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Opening Date & Time | 19/10/2026 16:00 | 25/10/2026 15:00 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 1. Definitions(aa)Intended Completion Date | The Intended Completion Date for the whole of the Works shall be 2027-06-30 | The Intended Completion Date for the whole of the Works shall be 2027-07-25 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 1. Definitions1.1(qq)StartDate | The Start Date shall be 2026-11-16 | The Start Date shall be 2026-12-11 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 13. Possession of the Site13.1 Possession of the Site |
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 2. Interpretation2.5. Sectional completion |
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 39. Commencement of Works39.1 Commencement of Works | Commencement Date of Works: 2026-11-01 | Commencement Date of Works:2026-11-26 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 41. Programme of Works41.2 Programme Update | The period between Programme updates is 15 | The period between Programme updates is 30 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 41. Programme of Works41.3 Withhold amount | The amount to be withheld for late submission of an updated Programme is 2000.000 | The amount to be withheld for late submission of an updated Programme is 20000.000 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC 82. As-built Drawings and Manuals82.1 As-built drawing date |
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Last date & time for Tender/Proposal Security Submission | 19/10/2026 15:50 | 25/10/2026 14:30 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Start Date(Lot No : 1) | 01/11/2026 | 02/12/2026 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Closing Date & Time | 19/10/2026 16:00 | 25/10/2026 15:00 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- |
The PE is Executive Engineer, Bagerhat WD Division, BWDB, Bagerhat. The Name of the Tender is:River Bank Protective Work from km 2.547 to km 2.797 = 0.250 km (Remaining Part) at Morrelganj Ferry Ghat area along the Right Bank of Panguchi River in C/W "Protection of Morrelganj Upazila sadar & Adjacent Areas from Erosion of Panguchi River & Re-excavation/Dredging of Bishkhali River in Bagerhat District" Under Bagerhat WD Division, BWDB,Bagerhat. Tender Ref:42.01.0100.617.44.001.24-592 Date: 24/09/2026 Lot No(s):M-04/02 [if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities] |
The PE is Executive Engineer, Bagerhat WD Division, BWDB, Bagerhat. The Name of the Tender is:River Bank Protective Work from km 2.547 to km 2.797 = 0.250 km (Remaining Part) at Morrelganj Ferry Ghat area along the Right Bank of Panguchi River in C/W "Protection of Morrelganj Upazila sadar & Adjacent Areas from Erosion of Panguchi River & Re-excavation/Dredging of Bishkhali River in Bagerhat District" Under Bagerhat WD Division, BWDB,Bagerhat. Tender Ref:42.01.0100.617.44.0001.26-592 Date: 24/09/2026 Lot No(s):M-04/02 [if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The minimum specific experience as a Prime Contractor or Subcontractor or ManagementContractor in construction works under public sector of at least onecontract(s) ofConstruction/Repair of revetment/river bank protection work/shore protectionwork/crossbar/Spur/groyne successfully completed within the last 5 years, each with a value of at least Tk. 84500000.00 BDT (Eight Crore Forty-Five Lakh Taka Only; years counting backward from the date of publication of IFT in the newspaper] |
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works under public sector of at least (01) one contract of Construction/ Repair of revetment/ River bank protection work/ Shore protection work/ Crossbar/ Spur/ Groyne successfully completed within the last 5 years, each with a value of at least Tk. 8,45,00,000.00 (Eight Crore Forty-Five Lakh Only); years counting backward from the date of publication of IFT in the newspaper. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover under public sector shall be greater than Tk. 168900000.00 BDT (Sixteen Crore Eighty-Nine Lakh Taka Only) over the best three (3) years in the last five (5) financial years. |
The required average annual construction turnover under public sector shall be greater than Tk. 16,80,00,000.00 (Sixteen Crore Eighty Lakh only) over the best three (3) years in the last five (5) financial years. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of financial resources as liquid asset or working capital or credit line(s) or specific credit commitment or in any combination of them, of the Tenderers shall be Tk 32200000.00 BDT (Three crore twenty-two lakh Taka only) |
The minimum amount of financial resources as liquid asset or working capital or credit line(s) or specific credit commitment or in any combination of them, of the Tenderers shall be Tk 2,80,00,000.00 (Two Crore Eighty Lakh only). |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The minimum capacity shall be Tk. 84500000.00 BDT (Eight Crore Forty-Five Lakh Taka Only ) |
The minimum capacity shall be Tk. 8,45,00,000.00 (Eight Crore Forty-Five Lakh only).
The following formulae shall be used to calculate the Tender Capacity |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience supported by CVs following the Form PW3-5.
[qualification of an alternative Construction Project Manager may also be requested] [for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience supported by CVs following the Form PW3-5.
[qualification of an alternative Construction Project Manager may also be requested] [for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | Tenderers shall own or have proven access to hire or lease of the major construction equipment, in full working order as follows:
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
Tenderers shall own or have proven access to hire or lease of the major construction equipment, in full working order as follows:
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- |
i. TIN certificate; |
The Tenderer shall submit with its Tender the following documents as a proof of fulfilling taxation obligations in accordance with ITT Sub Clause 5.5:
i. TIN certificate; |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- | The required information regarding claims under litigation shall be current or during the last 5 years |
The required information regarding claims under litigation shall be current or during the last 03 (Three) years. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- |
The required audit reports on the financial standing, such as profit and loss statements and balance |
The required audit reports on the financial standing, such as profit and loss statements and balance sheet shall be for the past 02 (two) years. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- | The amount of the Tender Security shall be Tk.2820000.00 BDT.
[for more than one lot in a package, the Tender Security for each lot may be determined on different percentage basis and , should be mentioned separately] |
The amount of the Tender Security shall be Tk.28,00,000.00 (Twenty-Eight Lakh only).
[for more than one lot in a package, the Tender Security for each lot may be determined on different percentage basis and , should be mentioned separately] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--E. Tender Submission-- |
For Tender submission purposes only, the Procuring Entity’s address is: The PE is Executive Engineer, Bagerhat WD Division, BWDB, Bagerhat.
The deadline for submission of Tenders is : |
For Tender submission purposes only, the Procuring Entity’s address is: The PE is Executive Engineer, Bagerhat WD Division, BWDB, Bagerhat.
The deadline for submission of Tenders is : As stated in Tender Notice. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--G. Contract Award-- | The biographical data of the Adjudicator is:
|
The biographical data of the Adjudicator is:
The hourly fee shall be Tk 5000 (Five Thousand only). |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Brief Description of Goods,Works or Service | M-04/02 |
M-04/02 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Tender/Proposal Security (Amount in BDT)(Lot No : 1) | 2820000.0 | 2800000 |