| Eligibility of Consultant
|
The Tenderer shall have the following qualifications:
a) The minimum of years of general experience of the Tenderer in the supply of Goods and related services as Supplier shall be 5 (Five) years*.
b) The Tenderer shall have a minimum specific experience as Supplier in supply of similar Goods (Lift) of at least 1 (One) contract successfully completed within the last 5 (Five) years*, with a value of at least Tk. 75,00,000.00 (Seventy Five Lac Only) under public or private sector.
c) The minimum amount of financial resources as liquid asset or working capital or credit line(s) or specific credit commitment or in any combination of them, of the Tenderers shall be Tk. 95,00,000.00 (Ninety Five Lac Only).
d) Up-to-date valid Trade License.
e) Up-to-date ABC/BC category Contractor & Electrical Supervisor license from Bangladesh Electrical Licensing Board.
f) Income Tax Assessment Year shall be FY 2024-25.
g) Up-to-date VAT registration certificate (BIN).
h) Authorization letter from lift manufacturer.
i) Sole Agent/Representative/ Distributorship certificate from lift manufacturer.
j) Catalogue & technical specifications of proposed lift.
k) Other qualifications stated in TDS & PCC.
l) PPA 2006 and PPR 2025 (with all amendments) shall be followed.
m) The Tenderer shall provide Three (03) years of monthly maintenance, unconditional technical support and genuine spare parts at their own cost under an onward agreement with CMP (the User Agency). The Retention money (security deposit) shall be retained by the PE for Three (03) years from the date of completion and commissioning of the lift.
n) Warranty Period : Three (03) years.
* Years counting backward from the date of publication of IFT in the newspaper.
|
The Tenderer shall have the following qualifications:
a) The minimum of years of general experience of the Tenderer in the supply of Goods and related services as Supplier shall be 5 (Five) years*.
b) The Tenderer shall have a minimum specific experience as Supplier in supply of similar Goods (Lift) of at least 1 (One) contract successfully completed within the last 5 (Five) years*, with a value of at least Tk. 75,00,000.00 (Seventy Five Lac Only) under public or private sector.
c) The minimum amount of financial resources as liquid asset or working capital or credit line(s) or specific credit commitment or in any combination of them, of the Tenderers shall be Tk. 95,00,000.00 (Ninety Five Lac Only).
d) Up-to-date valid Trade License.
e) Up-to-date ABC/BC category Contractor & Electrical Supervisor license from Bangladesh Electrical Licensing Board.
f) Income Tax Assessment Year shall be FY 2024-25.
g) Up-to-date VAT registration certificate (BIN).
h) Authorization letter from lift manufacturer.
i) Sole Agent/Representative/ Distributorship certificate from lift manufacturer.
j) Catalogue & technical specifications of proposed lift.
k) Other qualifications stated in TDS & PCC.
l) PPA 2006 and PPR 2025 (with all amendments) shall be followed.
m) The Tenderer shall provide Three (03) years of monthly maintenance, unconditional technical support and genuine spare parts at their own cost under an onward agreement with CMP (the User Agency). The Retention money (security deposit) shall be retained by the PE for Three (03) years from the date of completion and commissioning of the lift.
n) Warranty Period : Three (03) years.
* Years counting backward from the date of publication of IFT in the newspaper.
|
| TDS/PDS--D. e-Tender Preparation--
|
Income Tax Assessment Year shall be Financial Year 2025-2026. |
Income Tax Assessment Year shall be Financial Year 2024-2025.
|
| TDS/PDS--G. Contract Award--
|
The amount of Performance Security shall be ten (10) percent of the Contract Price.
The successful Tenderer shall furnish the Performance Security for the due performance of the Contract within [mention number of working days as per Rule 123(7) of the PPR 2025: 7/10/14] working days of issuance of the Notification of Award (NoA).
[• Within seven (7) working days, where the estimated cost does not exceed BDT 50 million (Taka five crore);
• Within ten (10) working days, where the estimated cost exceeds BDT 50 million (Taka five crore) but does not exceed BDT 250 million (Taka twenty-five crore);
• Within fourteen (14) working days, where the estimated cost exceeds BDT 250 million (Taka twenty-five crore).]
|
The amount of Performance Security shall be ten (10) percent of the Contract Price.
The successful Tenderer shall furnish the Performance Security for the due performance of the Contract within 7 working days of issuance of the Notification of Award (NoA).
|
| Brief Description of Goods,Works or Service
|
Supply, installation, testing & commissioning of 1 no 6 stop 1250 kg fire fighters' lift for CMP headquarters at Chattogram.
|
Supply, installation, testing & commissioning of 1 no 6 stop 1250 kg fire fighters' lift for CMP headquarters at Chattogram.
|