View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Dear Tenderer, Please submit the specification of item no. 4 & 5 as grid tied inverter instead of Hybrid type inverter. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | 1. Updated trade license, Tax certificate, BIN. 2. The tenderer shall have general working experience of at least 5 (Five) years. 3. A satisfactory completion of similar works of at least Tk 12.0 lac under 1 number of contract(s) over a period of 5 years shall be required. i. e Supply, Installation, Testing & Commissioning of on-grid solar power systems at least 5 KWp in government organization & goverment owned organization . 4.The required average annual construction turnover shall be greater than Tk 15.0 lac in best of 2 years over the last 5 years. 5.The minimum amount of liquid asset or working capital or credites facilities of the tenderer shall have tk 25.0 lac. 6.The work shall have to be completed by 45 days. 7. As per TDS, PCC |
1. Updated trade license, Tax certificate, BIN. 2. The tenderer shall have general working experience of at least 5 (Five) years. 3. A satisfactory completion of similar works of at least Tk 12.0 lac under 1 number of contract(s) over a period of 5 years shall be required. i. e Supply, Installation, Testing & Commissioning of on-grid solar power systems at least 5 KWp in government organization & goverment owned organization . 4.The required average annual construction turnover shall be greater than Tk 15.0 lac in best of 2 years over the last 5 years. 5.The minimum amount of liquid asset or working capital or credites facilities of the tenderer shall have tk 25.0 lac. 6.The work shall have to be completed by 45 days. 7. As per TDS, PCC |
| Brief Description of Goods,Works or Service | Supply, Installation, Testing & Commissioning of 3 units of 15 KWp capacity on grid solar power system at Bhangura, Ruppur & Kushtia and 1 unit of 10 KWp capacity on grid solar power system at Bheramara GK sub-station under GMD, Power Grid, Ishwardi. |
Supply, Installation, Testing & Commissioning of 3 units of 15 KWp capacity on grid solar power system at Bhangura, Ruppur & Kushtia and 1 unit of 10 KWp capacity on grid solar power system at Bheramara GK sub-station under GMD, Power Grid, Ishwardi. |