Amendment / Corrigendum No. : 1
|
| Amendment / Corrigendum Text : |
Due to unavoidable circumstances, Corrigendum Notice is issued for extension tender opening time. |
| Field Name |
Old Value |
New Value |
| Document last selling date & time
|
21/12/2014 17:00 |
24/12/2014 17:00 |
| Eligibility of Consultant
|
1. Tenderer must has to register on e-GP Portal with a valid trade license, TIN certificate.
2. Tendere only from Bangladesh can participate to the tender.
3. Payment will be made subject to allocation & availability of fund. But the work must be continued and completed within schedule time and proportionate progress must be achieved.
4.The tenderer has arrange the land for execution of works by his/her own initiative. In this regard no claim will be entertained.
Special Instructions (Mendatory)
1. Tenderer must submit the " Detail Breakdown of the Unit Rates or Prices quoted by the tenderer" after filling all 11 (Eleven) items of the red colored text area of the analysis template. Blank template is available at drawing section of tender document. Without filled analysis, tender wll be rejected.
2. Tenderer need to be submitted credit line/liquid assets certificate in the given format from the schedule bank. This certificate in other format will not be acceptable. Without this, tenderer will declared to be non-responsive. Given format also available at drawing section of tender document or it can be downloaded from CPTU web site of standard PW3 document.
|
1. Tenderer must has to register on e-GP Portal with a valid trade license, TIN certificate (Up to date).
2. Tendere only from Bangladesh can participate to the tender.
3. Payment will be made subject to allocation & availability of fund. But the work must be continued and completed within schedule time and proportionate progress must be achieved.
4.The tenderer has arrange the land for execution of works by his/her own initiative. In this regard no claim will be entertained.
Special Instructions (Mendatory)
1. Tenderer must submit the " Detail Breakdown of the Unit Rates or Prices quoted by the tenderer" after filling all 11 (Eleven) items of the red colored text area of the analysis template. Blank template is available at drawing section of tender document. Without filled analysis, tender wll be rejected.
2. Tenderer need to be submitted credit line/liquid assets certificate in the given format from the schedule bank. This certificate in other format will not be acceptable. Without this, tenderer will declared to be non-responsive. Given format also available at drawing section of tender document or it can be downloaded from CPTU web site of standard PW3 document.
|
| Opening Date & Time
|
22/12/2014 15:00 |
28/12/2014 14:30 |
| Meeting End Date & Time
|
21/12/2014 17:00 |
24/12/2014 17:00 |
| Meeting Start Date & Time
|
13/11/2014 16:30 |
22/12/2014 11:30 |
| Last date & time for Tender/Proposal Security Submission
|
22/12/2014 11:30 |
28/12/2014 11:30 |
| Start Date(Lot No : e-GP/RBP-20)
|
01/01/2015 |
08/01/2015 |
| Closing Date & Time
|
22/12/2014 12:00 |