View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Energy, Power and Minearal Resources Division : Power Division
Organization : West Zone Power Distribution Company Ltd (WZPDCL) Procuring Entity Name : Project Director's office of Extension & Augmentation of Power Distribution System Project
Procuring Entity Code : EAPDSP-5-5605-5 Procuring Entity District : Khulna
Procurement Nature : Goods Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : 27.22.4785.900.50.002.18.21(ID169140),dt:22.02.18 Tender/Proposal Status :
App ID : 88736 Tender/Proposal ID : 169140
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : EAPDSP-5-5605-5116 Project Name : Extension & Augmentation of Power Distribution System Project, Biddyut Bhaban Campus, Khulna
Tender/Proposal Package No. and Description : GD8 Lot-a FY-2017-18
Supply and delivery of 9 Meter 200 DAN SPC Pole in Khulna Area.
Category : Parts of electricity distribution or control apparatus; Electricity distribution and control apparatus;
Scheduled Tender/Proposal Publication
Date and Time :
22-Feb-2018 16:30 Tender/Proposal Document last selling /
downloading Date and Time :
01-Apr-2018 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
22-Feb-2018 18:30 Pre - Tender/Proposal meeting End
Date and Time :
27-Feb-2018 17:30
Tender/Proposal Closing
Date and Time :
02-Apr-2018 15:00 Tender/Proposal Opening
Date and Time :
02-Apr-2018 15:00
Last Date and Time for Tender/Proposal Security
Submission :
02-Apr-2018 13:00    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

a) The minimum of years of general experience of the Tenderer in the supply of Goods and related services as Supplier shall be 05 (five) calendar years.

b) The minimum specific experience as manufacturers in production and supply / Suppliers in Supply of 9 Meter 200 DAN SPC Pole or higher size of SPC Pole of minimum 2 (two) contract(s) successfully completed within the last 05 (five) calendar years from date of tender notice, each with a contract value of atleast BDT 0.70 (Zero point Seven Zero) Crore along with Performance Certificate of those satisfactorily completed supply within last 05 (five) calendar years from date of tender notice from Gov. electricity utility of Bangladesh.

c) The minimum Supply and/or production capacity of goods is/ are: At least 1/6th of the tendered quantity per month.

d) The minimum amount of liquid assets i.e. working capital or credit line(s) of the Tenderer shall be Twice of the quoted amount of each package.

e) The Bidder must submit the attested copy of Performance certificate, Otherwise that Performance Certificate may not be Considered.

For details, Please see the tender documents & Technical Specifications.

Brief Description of Goods and Related Service :

Supply and Delivery of 2000 Nos 9 Meter 200 DAN SPC Pole in Khulna Area.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 4000
Mode of Payment :
Tender/Proposal Security Valid Up to : 28-Aug-2018
Tender/Proposal Valid Up to : 31-Jul-2018
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
Lot-a Supply and delivery of 9 Meter 200 DAN SPC Pole in Khulna Area. Project Store at Khulna Area 700000 22-Jul-2018 18-Nov-2018
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Shafiqul Islam Designation of Official Inviting Tender/Proposal : Project Director
Address of Official Inviting Tender/Proposal :
Address: Biddyut Bhaban Campus, Boyra Main Road, Khulna
City: Khulna
Thana: Sonadanga
District: Khulna - 9000
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 041-731789
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 
Save As PDF