View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Tender data sheet & particular condition of contract is blank due to mistake. It is needed to prepare the TDS & PCC.All other terms & condition will remain same |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PCC--A. General-- | The Works consist of [state brief summary, including relationship to other Contracts under the Project] |
The Works consist of construction work plumbing worka etc [state brief summary, including relationship to other Contracts under the Project] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is |
The PE iss m shamim ahmed executive engineer,dphe
bagerhat |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at bagerhat pauroshava and is defined in drawings No: |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC Clause 40] |
The Start Date shall be 5/6/2018
[it is the last date when the Contractor shall commence execution of the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC Clause 40] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Project Manager is |
The Project Manager iss m shamim ahmed executive engineer,dphe
bagerhat |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is
The Development Partner is [Name of the DP] |
The PE is s m shamim ahmed executive engineer,dphe
bagerhat
The Development Partner is n/a |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);
[state date or dates of possession of site] |
Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s); 15 days after contract sign
[state date or dates of possession of site] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Contractual matters between the PE and the Contractor shall be decided by
[state only if other than the Project Manager] |
The Contractual matters between the PE and the Contractor shall be decided by project director
[state only if other than the Project Manager] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PEâ??s address for the purpose of communications under this contract is :
|
The PE’s address for the purpose of communications under this contract is :
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Materials, Equipments Plants and supplies shall not have their origin in the following countries:
[state countries, if applicable] |
Materials, Equipments Plants and supplies shall not have their origin in the following countries: israel
[state countries, if applicable] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible:
[state countries, if applicable] |
A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible:israel
[state countries, if applicable] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The period between Programme updates is [state interval]
[usually bi-monthly or quarterly depending on the nature of the Works] |
The period between Programme updates is monthly
[usually bi-monthly or quarterly depending on the nature of the Works] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually fifteen (15) days] |
The Contractor shall submit a Programme for the Works within 15 days days of signing the Contract.
[usually fifteen (15) days] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The amount to be withheld for late submission of an updated Programme is [state amount]. |
The amount to be withheld for late submission of an updated Programme is n/a |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--C. Quality Control-- | The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season]. |
The Defects Liability Period is 12 monthly
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season]. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The following additional events shall also be the Compensation Events:
|
The following additional events shall also be the Compensation Events: none
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- |
The Contract is not subject to price adjustment.
[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
[insert figure] non-adjustable component (coefficient A)
[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months] |
The Contract is not subject to price adjustment |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent.
|
The proportion of payments to be retained is 10 percent.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
|
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.1 percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.
[if early completion would provide benefits to the PE, this clause should remain, otherwise state â??Not Applicableâ?�. The bonus is usually numerically equal to the Liquidated Damages] |
The Bonus for the whole of the Works is zero percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.n/a
[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].
[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects] |
The Advance Payment shall be Tk zero and shall be paid to the Contractor not later than n/a. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The percentage for adjustment of Provisional Sums is
____% (_________percent) |
The percentage for adjustment of Provisional Sums is none
____% (_________percent) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The amount to be withheld for failing to produce â??as-builtâ?� drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]
[usually a very nominal amount] |
The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk 0.100
[usually a very nominal amount] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The date by which â??as-builtâ?� drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date] |
The date by which “as-built” drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the PEâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 20 percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- | The PE is [state name of PE]
The Name of the Tender is: Tender Ref: Lot No(s):
[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities] |
The PE is s m shanmim ahmed
The Name of the Tender is:Construction of 680 m3 Capacity Over Head Tank at Bageraht Pourashava under Gopalgonj & Bagerhat Pourashava Water Supply & Environmental Sanitation System Improvement Project Tender Ref:PD,G&B,PAUROSHAVA,MEMO NO-61,DATED-11/2/18 Lot No(s):01 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- | The source of public funds is
[state source, GoB or other source of funds]. |
The source of public funds is GOB |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- | The name of the Development Partner is
[state name of Development Partner] |
The name of the Development Partner is N/A |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- | Tenderers from the following countries are not eligible
[ state countries, if any ] |
Tenderers from the following countries are not eligible ISRAEL |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--A. General-- | Materials, Equipments and associated services from the following countries are not eligible: israel
[state countries, if any] |
Materials, Equipments and associated services from the following countries are not eligible: israel |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--B. e-Tender Document (e-TD)-- | Allowed to post clarification till [Date and Time] |
Allowed to post clarification till n/a |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--B. e-Tender Document (e-TD)-- |
A Pre-Tender meeting shall not be held
[delete whichever is not applicable] |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--B. e-Tender Document (e-TD)-- | Pre- Tender meeting [Date & Time] |
Pre- Tender meeting etarts on 4/4/18 and ends on 9/4/18 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be [state number] years. [a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper]
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least [state number] contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last [state number] years, each with a value of at least Tk. [state amount].
[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package] |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 years.
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works should have successfully completion of 200 cum OHT of at least 01 contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 05 years, each with a value of at least Tk. 200 lac |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The required average annual construction turnover shall be greater than Tk 200 lac over the last 05 years.
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 120 lac |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum Tender Capacity shall be: :[70%-80% of the official estimated cost]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package] |
The minimum Tender Capacity shall be: 210 lac tk |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : |
The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : as on 19.1 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount] |
The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its Tender the following additional documents:
|
The Tenderer shall submit with its Tender the following additional documents: n/a
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- |
The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
Iif prices shall be adjustable, the methodology for adjustment should be specified] |
The prices quoted by the Tenderer shall be fixed for the duration of the Contract. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--E. Tender e-Submission-- | The deadline for lodgement of e-Tenders is [state time, and identify a.m or p.m, i.e 10.30 a.m]
|
The deadline for lodgement of e-Tenders is 18/4/18,14:00 pm
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--G. Contract Award-- | The amount of Performance Security shall be [state percentage] percent of the Contract Price.
[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ] |
The amount of Performance Security shall be 10 percent of the Contract Price. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | tender data sheet & particular condition of contract is not made properly or not done It is needed to fill the tender data sheet & particular condition of contract |
| Field Name | Old Value | New Value |
|---|---|---|
| TDS/PDS--A. General-- | Materials, Equipments and associated services from the following countries are not eligible:
[state countries, if any] |
Materials, Equipments and associated services from the following countries are not eligible: israel
[state countries, if any] |