View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Tender/Proposal Document last selling /downloading Date and Time: 13-Nov-2013, 17.00 |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 03/11/2013 17:00 | 13/11/2013 17:00 |
| Opening Date & Time | 10/11/2013 16:00 | 17/11/2013 15:00 |
| Last date & time for Tender/Proposal Security Submission | 10/11/2013 12:00 | 17/11/2013 12:00 |
| Closing Date & Time | 10/11/2013 13:00 | 17/11/2013 13:00 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | GCC Clause 31. Liquidated Damages 31.1 The Contractor shall be liable to pay Liquidated Damages or in other words the Delay Damages to the PE at the rate per day as specified in the PCC for each day of delay from the Intended Completion Date, for the uncompleted Works or for any part thereof. The amount of Liquidated Damages or in other words Delay Damages is 0.05% of final Contract price of the uncompleted Works or any part there of it's per day of delay. |
| Field Name | Old Value | New Value |
|---|---|---|
| Opening Date & Time | 04/11/2013 15:00 | 10/11/2013 16:00 |
| Last date & time for Tender/Proposal Security Submission | 04/11/2013 12:00 | 10/11/2013 12:00 |
| Closing Date & Time | 04/11/2013 13:00 | 10/11/2013 13:00 |