Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | The PCC will be Changed as Described. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As Per ITT and TDS |
As Per ITT and TDS |
| Opening Date & Time | 11/02/2019 16:00 | 17/02/2019 16:00 |
| PCC--D. Cost Control-- | The following additional events shall also be the Compensation Events:
|
The following additional events shall also be the Compensation Events:None |
| PCC--D. Cost Control-- |
The Contract is not subject to price adjustment.
[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
[insert figure] non-adjustable component (coefficient A) [price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months] |
The Contract is not subject to price adjustment. |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent.
|
The proportion of payments to be retained is 5% percent. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
|
The amount of Liquidated Damages is 0.05 of ONE (1) percentof the contract value of the uncompleted works or any part thereof completed after expiry of the Intended Completion Date or extended Intended Completion Date, as applicable, per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (ten) percent of the final Contract Price of the whole of the Works |
| PCC--D. Cost Control-- | The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price. [if early completion would provide benefits to the PE, this clause should remain, otherwise state â??Not Applicableâ?�. The bonus is usually numerically equal to the Liquidated Damages] |
The Bonus for the whole of the Works is….percent of the final Contract Price per day of early completion.Not Applicable |
| PCC--D. Cost Control-- | The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date]. [for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects] |
The Advance Payment shall be Tk and shall be paid to the Contractor not later than: Not Applicable |
| PCC--D. Cost Control-- | The percentage for adjustment of Provisional Sums is
____% (_________percent) |
The percentage for adjustment of Provisional Sums is N/A |
| Closing Date & Time | 11/02/2019 16:00 | 17/02/2019 16:00 |
| Brief Description of Goods,Works or Service | RDRIDP/Naog/Manda-08/18-19 |
RDRIDP/Naog/Manda-08/18-19 |