1.As per TDS, PCC, PPR2008, PPA2006 and all its amendment
2. Tenderer quoted amount more than 10% Less or Above of Official Estimate will be non responsive 3.In case of Credit facility Tenderer must submit in the format Prescribed by CPTU (PW3-7) otherwise Non-responsive
4.Incomplete information in specific experience certificate may lead to non-responsive . 5. Material issued by the department will be deducted as per departmental rate .
6. Running bill will only be given after adequate water discharge from the Tube Well and Water Test Report have to be submitted to the respective Executive Engineer office. and Completion of Platform accurately etc.
7.TARA Sets should be tested by CROWN Agent
8. Performance Security 5- 25 percent
Installation of 55 Nos Deep TARA Tube Well (Non-Extractable) in Durgapur(15 nos), Kamakanda (19 nos) and Barhatta (21nos) and 11 Nos Ring Well in Durgapur (6 nos) and Kalmakanda (5 nos) under Village Water Supply Project During the FY 2018-19