View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | Tender security submission time change. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 06/01/2019 11:00 | 10/01/2019 11:00 |
| Opening Date & Time | 06/01/2019 13:00 | 10/01/2019 13:00 |
| Meeting End Date & Time | 02/01/2019 13:00 | 09/01/2019 13:00 |
| Last date & time for Tender/Proposal Security Submission | 01/01/2019 12:00 | 10/01/2019 12:00 |
| Closing Date & Time | 06/01/2019 13:00 | 10/01/2019 13:00 |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Corrigendum for opening date and Similar nature of work. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 01/01/2019 11:00 | 06/01/2019 11:00 |
| Opening Date & Time | 01/01/2019 13:00 | 06/01/2019 13:00 |
| Meeting End Date & Time | 31/12/2018 13:00 | 02/01/2019 13:00 |
| Closing Date & Time | 01/01/2019 13:00 | 06/01/2019 13:00 |
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 years. [a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper] The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of 1 or 2 (One/two) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (five) years, Summation of this two contracts with a value of at least Tk. 4,00,00,000.00 (Four Crores Only). Earth Work should be treated as specific experience. |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of 1 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 10 (ten) years, with a value of at least Tk. 4,25,00,000.00 (Four Crores twenty five lakh Only). Earth Work (river/ khal/ canal/ embankment/ earthen road), Spur, Groyne, Revetment, Regulator, Rubber dam, Sluice, Siphon, Aquiduct, Bridge, Culvert construction/reconstruction should be treated as specific experience. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Change/Correction in BoQ. |