View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Salvage Materials Deduction Item Code 02/02/05 Unit Rate Tk.3897425.00 Per Cum Instead of Item Code 02/02/05 Unit Rate Tk.175.00 Per Cum |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : |
The Minimum specific experience: Instead of
The Minimum specific experience: |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | Any/All Tenderers who have registration in Government e-GP system may participate in the Tender provided that they have to full fill the criteria as stated in Tender Data Sheet (TDS). If the Total Quoted Amount is more than 10% less/above than the Official Cost Estimate, the Tender/Tender(s) will be rejected. Tenderers must upload analysis of their quoted rates. Latest Amendment of PPA 2006 and PPR 2008 will be applicable. Experience as a sub-contractor or management contractor shall not be considered for this tender.
As per circular of CE, RHD. Vide memo215-CE, Date-06/08/17 |
Any/All Tenderers who have registration in Government e-GP system may participate in the Tender provided that they have to full fill the criteria as stated in Tender Data Sheet (TDS). If the Total Quoted Amount is more than 10% less/above than the Official Cost Estimate, the Tender/Tender(s) will be rejected. Tenderers must upload analysis of their quoted rates. Latest Amendment of PPA 2006 and PPR 2008 will be applicable. Experience as a sub-contractor or management contractor shall not be considered for this tender.
As per circular of CE, RHD. Vide memo215-CE, Date-06/08/17 |
| Brief Description of Goods,Works or Service | Construction of 645.015m Sonahat Bridge over the River Dudhkumar, 2.32 Km approach Road, 3nos Box Culvert, Earth Work, protective work with CC Block, an Engineer's Site Office as per design and direction of E/Ch and other related works . |
Construction of 645.015m Sonahat Bridge over the River Dudhkumar, 2.32 Km approach Road, 3nos Box Culvert, Earth Work, protective work with CC Block, an Engineer's Site Office as per design and direction of E/Ch and other related works . |