View IFT /PQ / REOI / RFP / PPS Notice Details ( Meeting Doc. Available. )
|
Amendment / Corrigendum No. : 6
|
|
| Amendment / Corrigendum Text : | This is to notify for all concerned that the tender invited: ID No.:274727 is hereby amended as stated below due to unavoidable circumstances: 1) Tender Last Selling Date & Time: 17/04/2019; 17.00 instead of 10/04/2019; 17.00 2) Tender Closing Date & Time: 18/04/2019; 13.00 instead of 11/04/2019; 13.00 3)Tender Opening Date & Time: 18/04/2019; 13.00 instead of 11/04/2019; 13.00 4) Last Date and Time for Tender Security submission: 18/04/2019; 12.00 instead of 11/04/2019; 12.00 All other terms and conditions of the tender will remain unchanged.The Corrigendum shall be part and parcel of the tender. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 10/04/2019 17:00 | 17/04/2019 17:00 |
| Opening Date & Time | 11/04/2019 13:00 | 18/04/2019 13:00 |
| Last date & time for Tender/Proposal Security Submission | 11/04/2019 12:00 | 18/04/2019 12:00 |
| Closing Date & Time | 11/04/2019 13:00 | 18/04/2019 13:00 |
|
Amendment / Corrigendum No. : 5
|
|
| Amendment / Corrigendum Text : | Due to unavoidable circumstances, The Bill of Quantities for fixed rate - Provisional Sum (BOQ SL.NO-46) only is hereby cancelled. New fixed rate Provisional Sum BOQ Form Prepared. |
|
Amendment / Corrigendum No. : 4
|
|
| Amendment / Corrigendum Text : | Due to unavoidable circumstances, The Bill of Quantities for fixed rate - Provisional Sum only is hereby cancelled. New fixed rate Provisional Sum BOQ Form Prepared. |
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | This is to notify for all concerned that the tender documents: 1) Tender Data Sheet (TDS) : ITT Clause: 15.1(a),15.1(b),16.1(b),16.1(c),17.1,18.1,30.1 and 2) Particulars Condition of Contract (PCC) : GCC Clause 19.1 & some additional/modified forms (Form-1 to Form-7) is hereby amended as per attached documents in TDS , PCC & Amendment section due to unavoidable circumstances. All other terms and conditions of the tender will remain unchanged.The Corrigendum shall be part and parcel of the tender. |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PCC---- | GCC Clause 19.1(Contractor’s Personnel) [Amended]: The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred to in the PCC, to carry out the functions stated in the Schedule or other personnel approved by the Project Manager. A. During Construction The Technical Personnel for construction work are attached in Amendment section. |
GCC Clause 19.1(Contractor's Personnel) [Amended]: The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred to in the PCC, to carry out the functions stated in the Schedule or other personnel approved by the Project Manager. A. During Construction The Technical Personnel for construction work are attached in Amendment section. |
||||||||||||||||||||||||||||
| TDS/PDS---- | ITT 30.1 Technical proposal must include:
2. Equipment: The list of required equipment details is as specified in TDS 18.1. 3. Personnel: The list of required personnel details is as specified in TDS 17.1. 4. Schedule: Schedule of the activities to be performed should be submitted graphically. |
ITT 30.1 Technical proposal must include:
2. Equipment: The list of required equipment details is as specified in TDS 18.1. 3. Personnel: The list of required personnel details is as specified in TDS 17.1. 4. Schedule: Schedule of the activities to be performed should be submitted graphically. |
||||||||||||||||||||||||||||
| TDS/PDS---- | ITT 30.1 Technical proposal must include:
2. Equipment: The list of required equipment details is as specified in TDS 18.1. 3. Personnel: The list of required personnel details is as specified in TDS 17.1.
4. Schedule: Schedule of the activities to be performed should be submitted graphically. |
ITT 30.1 Technical proposal must include:
2. Equipment: The list of required equipment details is as specified in TDS 18.1. 3. Personnel: The list of required personnel details is as specified in TDS 17.1.
4. Schedule: Schedule of the activities to be performed should be submitted graphically. |
||||||||||||||||||||||||||||
| TDS/PDS---- | ITT Clause-18.1(Equipment Capacity) [Amended]: Tenderer shall own or have proven access to hire or lease of the major construction equipment, in full working order which is attached in Amendmend section. |
ITT Clause-18.1(Equipment Capacity) [Amended]: Tenderer shall own or have proven access to hire or lease of the major construction equipment, in full working order which is attached in Amendment section. |
||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | a) The minimum number of years of general experience of the tenderer in the construction works as Prime Contractor shall be 5 (Five) years, counting backward from the date of publication of IFT in the newspaper/e-GP web portal including experience of all types of works as listed in ITT 1, brief description of the works. b) The minimum specific experience as a prime Contractor in similar improvementworks of at least 1(one) contract(s) successfully completed within the last 5(five) years, with a value of at least 27,00,00000.00 (Taka Twenty Seven Crore Only); counting backward from the date of publication of IFT in the in the e-GP web portal/ newspaper. The similarity of Tendererâ??s experience shall be based on improvement of minimum 16 kilometers or 62100.00 sqm(pavement work without shoulder) of road works in single contract. |
a) The minimum number of years of general experience of the tenderer in construction works as prime contractor or Joint Venture, Consortium or Associations (JVCA) partner shall be five (5) years, counting backward from the date of publication of IFT in the e-GP web portal/ newspaper, including experience of all types of works as listed in ITT 1, brief description of the works. b) The minimum specific experience as a prime contractor or JVCA partner in construction works of a nature, complexity and methods/construction technology similar to the proposed Works in at least one (1) contract successfully completed within the last seven (7) years , where the value of the Tenderer’s participation exceeds Tk. 27,00,00000.00 (Taka Twenty Seven Crore Only); counting backward from the date of publication of IFT in the e-GP web portal/ newspaper. The similarity of tenderer’s experience shall be based on road works or road improvements works.
(The certificatet to be submitted according to the attached format, Form 1, and Information to be submitted according to the Form 2 attached in the amendment section.) |
||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | (a) The required average annual construction turnover (AACT) i.e. total certified payments received for contracts in progress or completed shall be greater than 31,25,00000.00 (Taka Thirty One Crore Twenty Five Lac Only) over the last 05 (five) years, (years counting backward from the date of publication of IFT in the e-GP web portal)
(b) The minimum amount of liquid assets (LA) or working capital or credit facilities or credit line(s) of the Tenderer shall be 5,25,00000.00 (Taka Five CroreTwenty Five Lac Only) net of other contractual commitments. |
(a) The required average annual construction turnover (AACT) i.e. total certified payments received for contracts in progress or completed shall be greater than 31,25,00000.00 (Taka Thirty One Crore Twenty Five Lac Only) over the last 05 (five) years, (years counting backward from the date of publication of IFT in the e-GP web portal) (b) The minimum amount of liquid assets (LA) or working capital or credit facilities or credit line(s) of the Tenderer shall be Tk5,25,00000.00 (Taka Five Crore Twenty Five Lac Only) net of other contractual commitments to be provided in form-6: Financial requirement for current contract commitment attached in section-7 [Bank Statement of day end closing balance / credit line(s) issued by any scheduled Bank of Bangladesh not earlier than 28 (twenty-eight) days prior to the day of the original deadline for submission of Tenders for the Contract. Credit line(s) issued by any scheduled Bank of Bangladesh in the format as specified in Form (PW3–7) which is attached in section-8 without any alteration.
Credit facilities should be substantiated by credit sanction letter from any scheduled Bank of Bangladesh. (c) All pending litigation and arbitration, if any, shall be treated as resolved against the bidder and so shall in total not represent more than 50% of the Bidder’s net worth calculated as the difference between total assets and total liabilities. (informationto be provided in form-7: Pending Litigation and arbitration attached in the amendment section.) |
||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The Contractor shall employ (mandatory) for the construction work the technical personnel named and approved by the Project Manager. The Project Manager will approve any proposed replacement of technical personnel only if their relevant qualifications and abilities are substantially equal to or better than those of the personnel stated in the Contract Data.
|
The Contractor shall employ (mandatory) for the construction work the technical personnel named and approved by the Project Manager. The Project Manager will approve any proposed replacement of technical personnel only if their relevant qualifications and abilities are substantially equal to or better than those of the personnel stated in the Contract Data.
(Information to be submitted according to the Form 4 attached in the Amendment section) |
| Amendment / Corrigendum/ Addendum No. : | 3 | ||||
| S. No. | File Name | File Description | File Size (in KB) |
||
|---|---|---|---|---|---|
| 1 | Additional Forms to be filled by Tenderer.rar | Additional Form to be filled by Tenderer | 88238 | ||
| 2 | Amendment to Tender Document (CW-34) - 20-3-19.docx | Amendment Details of TDS and PCC | 61766 | ||
| 3 | Form 1_Completion Certificate format.docx | FORM-1 | 24898 | ||
| 4 | Form 2_Similar Exp. Information.xlsx | FORM-2 | 15558 | ||
| 5 | Form 3_Turnover Information.xlsx | FORM-3 | 16170 | ||
| 6 | Form 4_Personnel Information.xlsx | FORM-4 | 13390 | ||
| 7 | Form 5_Equipment Information.xlsx | FORM-5 | 14134 | ||
| 8 | form-6_Financial requirement for current contract commitment.xlsx | FORM-6 | 14670 | ||
| 9 | form-7_Pending Litigation and Arbitration.xlsx | FORM-7 | 14396 | ||
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | This is to notify for all concerned that the tender invited: ID No.:274727 is hereby amended as stated below due to unavoidable circumstances: 1) Tender Last Selling Date & Time: 10/04/2019; 17.00 instead of 19/03/2019; 17.00 2) Pre-tender Meeting(On Line) End Date & Time: 28/03/2019; 17.00 instead of 07/03/2019; 17.00 3) Tender Closing Date & Time: 11/04/2019; 13.00 instead of 20/03/2019; 13.00 4)Tender Opening Date & Time: 11/04/2019; 13.00 instead of 20/03/2019; 13.00 5) Last Date and Time for Tender Security Submission: 11/04/2019; 12.00 instead of 20/03/2019; 12.00 All other terms and conditions of the tender will remain unchanged.The Corrigendum shall be part and parcel of the tender. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 19/03/2019 17:00 | 10/04/2019 17:00 |
| Opening Date & Time | 20/03/2019 13:00 | 11/04/2019 13:00 |
| Meeting End Date & Time | 07/03/2019 17:00 | 28/03/2019 17:00 |
| Last date & time for Tender/Proposal Security Submission | 20/03/2019 12:00 | 11/04/2019 12:00 |
| Closing Date & Time | 20/03/2019 13:00 | 11/04/2019 13:00 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | This is to notify for all concerned that the tender invited: ID No.:274727 is hereby amended as stated below due to unavoidable circumstances: 1) Tender Last Selling Date & Time: 19/03/2019; 17.00 instead of 04/03/2019; 17.00 2) Pre-tender Meeting(On Line) End Date & Time: 07/03/2019; 17.00 instead of 25/02/2019; 17.00 3) Tender Closing Date & Time: 20/03/2019; 13.00 instead of 05/03/2019; 13.00 4)Tender Opening Date & Time: 20/03/2019; 13.00 instead of 05/03/2019; 13.00 All other terms and conditions of the tender will remain unchanged.The Corrigendum shall be part and parcel of the tender. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 04/03/2019 17:00 | 19/03/2019 17:00 |
| Eligibility of Consultant | As stated in TDS. |
As stated in TDS. |
| Opening Date & Time | 05/03/2019 13:00 | 20/03/2019 13:00 |
| Meeting End Date & Time | 25/02/2019 17:00 | 07/03/2019 17:00 |
| Last date & time for Tender/Proposal Security Submission | 05/03/2019 12:00 | 20/03/2019 12:00 |
| Closing Date & Time | 05/03/2019 13:00 | 20/03/2019 13:00 |
| Brief Description of Goods,Works or Service | 01. Improvement of Hatibandha - Daikhowa Hat Road from ch.00m - 9963m under Hatibandha Upazila, (Road ID : 52332002),District:Lalmonirhat. 02. Improvement of ZR at Baninagar to Daikhowa GC Road from Ch.00m - 3650m under Kaliganj Upazila, (Road ID : 152392003),District:Lalmonirhat. 03. Improvement of ZR at Baninagar - Durakuti GC Road from Ch.00m -15610m under Kaliganj Upazila, (Road ID : 152392001),District:Lalmonirhat. 04. Improvement of Burirhat GC - Velabari GC Road from Ch.4395m - 8785m under Aditmari Upazila, (Road ID : 152022003), District:Lalmonirhat. (Total Cost Of Salvage Materials Tk. 1,55,55,791.000) |
01. Improvement of Hatibandha - Daikhowa Hat Road from ch.00m - 9963m under Hatibandha Upazila, (Road ID : 52332002),District:Lalmonirhat. 02. Improvement of ZR at Baninagar to Daikhowa GC Road from Ch.00m - 3650m under Kaliganj Upazila, (Road ID : 152392003),District:Lalmonirhat. 03. Improvement of ZR at Baninagar - Durakuti GC Road from Ch.00m -15610m under Kaliganj Upazila, (Road ID : 152392001),District:Lalmonirhat. 04. Improvement of Burirhat GC - Velabari GC Road from Ch.4395m - 8785m under Aditmari Upazila, (Road ID : 152022003), District:Lalmonirhat. (Total Cost Of Salvage Materials Tk. 1,55,55,791.000) |