Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Contract Period needs to extend |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 03/12/2020 | 03/06/2021 |
| Document last selling date & time | 06/03/2019 17:00 | 13/03/2019 17:00 |
| Eligibility of Consultant | a. The tenderer must submit up to date authorization letter for submission against this tender ID. All other information are available in TDS |
a. The tenderer must submit up to date authorization letter for submission against this tender ID. All other information are available in TDS |
| Opening Date & Time | 07/03/2019 12:00 | 14/03/2019 12:00 |
| PCC--A. General-- | The Intended Completion Date for the whole of the Works shall be - 18(eighteen) months from the commence date. Note: Due to monsoon, any type of bituminous work will remain stop during 15 June to 15 September |
The Intended Completion Date for the whole of the Works shall be - 24(Twenty Four) months from the commence date. Note: Due to monsoon, any type of bituminous work will remain stop during 15 June to 15 September |
| Last date & time for Tender/Proposal Security Submission | 07/03/2019 11:00 | 14/03/2019 11:00 |
| Closing Date & Time | 07/03/2019 12:00 | 14/03/2019 12:00 |
| Brief Description of Goods,Works or Service | Construction of 4-Lane Connecting Road with Service Road in both side from Patuakhali-Kuakata Highway Road (Rajopara) to Payra 1320 MW Thermal Power Plant at Dhankhali (Tiakhali) Kalapara, Patuakhali, under Road Division Patuakhali during the FY 2018-19. |
Construction of 4-Lane Connecting Road with Service Road in both side from Patuakhali-Kuakata Highway Road (Rajopara) to Payra 1320 MW Thermal Power Plant at Dhankhali (Tiakhali) Kalapara, Patuakhali, under Road Division Patuakhali during the FY 2018-19. |