Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | 17th March 2019 is office holiday, so the closing and opening date of tender need to be changed. |
| Field Name | Old Value | New Value |
|---|---|---|
| Opening Date & Time | 17/03/2019 12:20 | 21/03/2019 12:20 |
| Closing Date & Time | 17/03/2019 12:20 | 21/03/2019 12:20 |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | The date and time of last selling date of this tender has been set on 5.30 am 10th March 2019. Due to office holiday on Friday and Saturday (8th & 9th March), many contractors could not purchase the tender security and the time for last selling date has to be changed as some contractors has already complained against this. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 26/05/2019 | 10/06/2019 |
| Document last selling date & time | 10/03/2019 05:30 | 13/03/2019 17:30 |
| Eligibility of Consultant | 1. Minimum 03 years of general experience in similar construction works as a Prime Contractor or Sub Contractor. 5. A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience: 6.Up to date Trade License. |
1. Minimum 03 years of general experience in similar construction works as a Prime Contractor or Sub Contractor.
5. A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:
6.Up to date Trade License. |
| Opening Date & Time | 12/03/2019 12:20 | 17/03/2019 12:20 |
| Last date & time for Tender/Proposal Security Submission | 10/03/2019 05:30 | 13/03/2019 17:30 |
| Start Date(Lot No : 1) | 13/03/2019 | 27/03/2019 |
| Closing Date & Time | 12/03/2019 12:20 | 17/03/2019 12:20 |
| Brief Description of Goods,Works or Service | Construction of Shore Protection work including Walkway ,fencing and demarcation pillar as necessary as per drawing in both side of Ramchandrapur Khal, Chainage 1+404 to 1+904 = 500 Meter . ( Package-2) WD-02. |
Construction of Shore Protection work including Walkway ,fencing and demarcation pillar as necessary as per drawing in both side of Ramchandrapur Khal, Chainage 1+404 to 1+904 = 500 Meter . ( Package-2) WD-02. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | In Tender Data Sheet JV requirements in ITT Clause No 18.1 & 18.2 have to change to comply with the requirements in STD (PW 3). |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| TDS/PDS--C. Qualification Criteria-- | The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : N/A |
The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :
|
||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | JVCA: Not Applicable. |
JVCA: Maximum number of partners in the JV shall be 3 |