Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Unavoidable Circumstances |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Completion Date(Lot No : 01) | 15/04/2020 | 30/01/2020 | ||||||||||||||||||||||||||||
| Eligibility of Consultant | As stated in ITT |
As stated in ITT |
||||||||||||||||||||||||||||
| PCC--A. General-- | Intended Completion Date is: 365 days from the date of commencement. |
Intended Completion Date is: 270 days from the date of commencement. |
||||||||||||||||||||||||||||
| PCC--A. General-- | The minimum insurance cover shall be:
|
The minimum insurance cover shall be:
|
||||||||||||||||||||||||||||
| PCC--A. General-- | Other documents forming part of the Contract are; i. Agreed Technical Proposal; ii. The Schedule of Key Personnel; iii.Work Program; iv. Joint Venture Agreement ( if applicable); v.Joint Venture Information Sheet (if applicable); vi. Insurance. |
Other documents forming part of the Contract are; i. The Schedule of Key Personnel; ii.Work Program; iii Joint Venture Agreement ( if applicable); iv.Joint Venture Information Sheet (if applicable); v. Insurance. |
||||||||||||||||||||||||||||
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is 20% (Twenty percent). In case of Front Loaded contract, additional performance security may also be forfeited. |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 10 (Ten) percent in normal case; but 20% (Twenty) Percent in case of front loading or if the tender is unbalanced for any reason. |
||||||||||||||||||||||||||||
| Start Date(Lot No : 01) | 15/04/2019 | 30/04/2019 | ||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its Tender the following additional documents: â?¢ Technical proposal as stated under ITT Clause 30. |
The Tenderer shall submit with its Tender the following additional documents: • Technical proposal -Not Applicable |
||||||||||||||||||||||||||||
| Brief Description of Goods,Works or Service | e-Tender/NBIDGPS/KHU/KHU/2018-2019/W1.03557 |