View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | Due to unaboidable circumstances Modify Tender security receiving date Modify work completion date |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 01) | 15/05/2017 | 15/11/2016 |
| Document last selling date & time | 28/09/2015 17:00 | 01/10/2015 17:00 |
| Opening Date & Time | 29/09/2015 12:05 | 04/10/2015 12:05 |
| Last date & time for Tender/Proposal Security Submission | 21/09/2015 11:00 | 01/10/2015 17:00 |
| Closing Date & Time | 29/09/2015 12:00 | 04/10/2015 12:00 |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Important structural & architectural drawings are attached here |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 01) | 30/04/2017 | 15/05/2017 |
| Document last selling date & time | 20/09/2015 17:00 | 28/09/2015 17:00 |
| Opening Date & Time | 21/09/2015 12:05 | 29/09/2015 12:05 |
| Meeting End Date & Time | 14/09/2015 17:00 | 17/09/2015 17:00 |
| Start Date(Lot No : 01) | 01/11/2015 | 15/11/2015 |
| Closing Date & Time | 21/09/2015 12:00 | 29/09/2015 12:00 |
| Amendment / Corrigendum/ Addendum No. : | 2 | ||||
| S. No. | File Name | File Description | File Size (in KB) |
||
|---|---|---|---|---|---|
| 1 | Floor Plan.rar | Drawing-Floor plan | 823264 | ||
| 2 | Structural Drawing.rar | Structural Drawing | 1690418 | ||
| 3 | Elevation.rar | Elevation | 731890 | ||
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Due to unaboidable circumstances Modified TDS & Modified PCC |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--D. Cost Control-- | The Contract is not subject to price adjustment. Mode of Payments: In case of front loading running payment = (Official rate + official rate x average rate) |
The Contract is not subject to price adjustment. Mode of Payments: In case of front loading (i) The rates of item having above than the average rate(amount in in percentage higher than the approved official estimated cost) shall be paid on successful completion at a rate equal to official rate of individual item plus official rate of that item multiplied by average rate (i.e Official rate + official rate x average rate) during running payments. (ii)The rates of items having above than the average rate shall be paid on successful completion at a rate quoted by the contractor during final payment. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is0.05 percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works.
If front loaded then it will be 20(Twenty) percent. |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is0.05 percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works.
|