View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | PCC Correction |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Eligibility of Consultant | As per ITT of Tender Document |
As per ITT of Tender Document |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at Upazila: Chatmohar, District : Pabna |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Works consist of [state brief summary, including relationship to other Contracts under the Project] |
The Works consist of General & Site Facilities, Earth Works,, Structural Works,RCC works, Sanitary Works, Electrical Works, Painting Works, and Environment Mitigation & Enhancement Works (as per Specification, BOQ and Drawings |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Project Manager is
|
The Project Manager is
|
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC Clause 40] |
The Start Date shall be within 7 (seven) days from the date of commencement of work. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The original Contract price is [insert the amount in the NOA] |
The original Contract price is the same as total quoted price at BOQ. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is |
The Intended Completion Date for the whole of the Works shall be 365 days from the date of commencement. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is The Development Partner is [Name of the DP] |
The Procuring Entity is The Development Partner is [:None |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);
[state date or dates of possession of site] |
Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s); |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;
[insert name(s)] |
Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor; |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Sectional Completion Dates are:
[state part of the works and the corresponding dates, if applicable] |
The Sectional Completion Dates are:N/A |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Nominated Subcontractor(s) named below;
____[insert name(s)]___________________________________________
[state none ,if not applicable] |
Nominated Subcontractor(s) named below; |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Contractual matters between the PE and the Contractor shall be decided by
[state only if other than the Project Manager] |
The Contractual matters between the Procuring Entity and the Contractor shall be decided by Project Director. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PEâ??s address for the purpose of communications under this contract is :
|
The Procuring Entity’s address for the purpose of communications under this contract is :
Executive Engineer
|
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The minimum insurance cover shall be:
|
The minimum insurance cover shall be:
|
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Materials, Equipments Plants and supplies shall not have their origin in the following countries:
[state countries, if applicable] |
Materials, Equipments Plants and supplies shall not have their origin in the following countries:Israel |
||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible:
[state countries, if applicable] |
A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible:Israel |
||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually fifteen (15) days] |
The Contractor shall submit a Programme for the Works within 14 (Fourteen) days of signing the Contract. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The amount to be withheld for late submission of an updated Programme is [state amount]. |
The amount to be withheld for late submission of an updated Programme is 5% of the next payment certificate. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The period between Programme updates is [state interval]
[usually bi-monthly or quarterly depending on the nature of the Works] |
The period between Programme updates is 90 (Ninety) days |
||||||||||||||||||||||||||||||||||||||||||
| PCC--C. Quality Control-- | The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season]. |
The Defects Liability Period is 12 (Twelve) Months |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The following additional events shall also be the Compensation Events:
|
The following additional events shall also be the Compensation Events:None |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- |
The Contract is not subject to price adjustment.
[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
[insert figure] non-adjustable component (coefficient A)
[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months] |
The Contract is not subject to price adjustment. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent.
|
The proportion of payments to be retained is 5% (Five percent) for each payment. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
|
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.05 (zero point zero five) percent of its Contract price per day of delay. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.
[if early completion would provide benefits to the PE, this clause should remain, otherwise state â??Not Applicableâ?�. The bonus is usually numerically equal to the Liquidated Damages] |
The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].
[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects] |
The Advance Payment shall be Tk. [insert amount] and shall be paid to the Contractor not later than [insert date]: Not Applicable |
||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The percentage for adjustment of Provisional Sums is
____% (_________percent) |
The percentage for adjustment of Provisional Sums is ; None |
||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The date by which â??as-builtâ?� drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date] |
The date by which “as-built” drawings are required is 07 (seven) days before the Issuance of Completion Certificate. |
||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The amount to be withheld for failing to produce â??as-builtâ?� drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]
[usually a very nominal amount] |
The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk :N/A |
||||||||||||||||||||||||||||||||||||||||||
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the PEâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 20 (Twenty) percent [When additional performance security is applicable due to the tender is significantly below the official estimated cost or unbalanced as a result of front loading 20% will be replaced by “Additional performance security plus 20%”] |
||||||||||||||||||||||||||||||||||||||||||
| PCC--G. Claims, Disputes and Arbitration-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; |
||||||||||||||||||||||||||||||||||||||||||
| PCC--G. Claims, Disputes and Arbitration-- |
The Adjudicator jointly appointed by the parties is:
In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Project Managers, Bangladesh. |
The Adjudicator jointly appointed by the parties is:Fixed by PE & Contractor.
In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Engineers Bangladesh (IEB), Bangladesh. |
||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
||||||||||||||||||||||||||||||||||||||||||
| Brief Description of Goods,Works or Service | Construction of Two2 Storied Rural Market Building with 04 Storied foundation in Mathurapur Hat under Chatmohar Upazila,District :Pabna. |
Construction of Two2 Storied Rural Market Building with 04 Storied foundation in Mathurapur Hat under Chatmohar Upazila,District :Pabna. |