View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Amendment/ Corrigendum 1 |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As per ITT, TDS, PCC, GCC, PPA, PPR and all of its Amendment Upozilla - Purbadhala |
As per ITT, TDS, PCC, GCC, PPA, PPR and all of its Amendment Upozilla - Purbadhala |
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is twelve (12) months |
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
6. The following additional events shall also be the Compensation Events: |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is 10 percent. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 01 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)] |
The required average annual construction turnover shall be greater than Tk 20.00 lac over the best three (3) years in the last five (5) years
[ the required average annual construction turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)] |
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.] |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 20.00 lac
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.] |
| TDS/PDS--C. Qualification Criteria-- | A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required. [the minimum value of the similar works under a single or multiple number of contract(s) is recommended to be between 50 and 75 percent of the estimated cost, rounded off to nearest Taka thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package] |
A satisfactory completion of similar works of at least Tk 20 .00 lac under 01 no of contract(s) over a period of last 05 years shall be required. |
| Brief Description of Goods,Works or Service | Construction of 5 Nos RCC WASH BLOCK FT Boys & MTGirls including 2 Nos Inspection Pits 1 Nos Soak Well & 1 Nos Septic Tank with all Sanitary and Electrical Works under Need Based Infrastructure Development of Government Primary Schools Project 1 st phase NBIDGPS-1 at specified Primary Schools of Purbadhala Upozilla during the FY 2019-2020 |
Construction of 5 Nos RCC WASH BLOCK FT Boys & MTGirls including 2 Nos Inspection Pits 1 Nos Soak Well & 1 Nos Septic Tank with all Sanitary and Electrical Works under Need Based Infrastructure Development of Government Primary Schools Project 1 st phase NBIDGPS-1 at specified Primary Schools of Purbadhala Upozilla during the FY 2019-2020 |