View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Amendment for correction of Bill of Quantities (Fixed rates items ) under section 6 Sl no. 4. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 21/10/2019 11:00 | 27/10/2019 11:00 |
| Eligibility of Consultant | Tenders from all eligible countries (a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five) years. (b) A satisfactory completion of similar works of at least Tk. 150.00 Lac only under summation of maximum 1 (One) numbers of contracts over a period of last 5 (Five) years shall be required. (c) The required average annual construction turnover (payment certificates will be considered) shall be greater than Tk. 250.00 Lac only over the last 5 (Five) years (according to Form 3_Turnover Information attached section 7). (d) The minimum amount of liquid asset ie Bank Statement or Credit Facilities of the Tenderer shall be Tk. 50.00 Lac only (Bank Statement or Credit Facilities issued not more than 28 (twenty eight) days prior to the day of original deadline for submission of Tenders for this Contract. ). (e) The minimum Tender capacity shall be Tk. 250.00 Lac only (according to the Form 6_Existing Work. Information attached section 7). (f) Personnel Capacity & Equipment List state in the TDS (according to the Form 4_Personnel Information & the Form 5_Equipment Information attached section 7). |
Tenders from all eligible countries (a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five) years. (b) A satisfactory completion of similar works of at least Tk. 150.00 Lac only under summation of maximum 1 (One) numbers of contracts over a period of last 5 (Five) years shall be required. (c) The required average annual construction turnover (payment certificates will be considered) shall be greater than Tk. 250.00 Lac only over the last 5 (Five) years (according to Form 3_Turnover Information attached section 7). (d) The minimum amount of liquid asset ie Bank Statement or Credit Facilities of the Tenderer shall be Tk. 50.00 Lac only (Bank Statement or Credit Facilities issued not more than 28 (twenty eight) days prior to the day of original deadline for submission of Tenders for this Contract. ). (e) The minimum Tender capacity shall be Tk. 250.00 Lac only (according to the Form 6_Existing Work. Information attached section 7). (f) Personnel Capacity & Equipment List state in the TDS (according to the Form 4_Personnel Information & the Form 5_Equipment Information attached section 7). |
| Opening Date & Time | 21/10/2019 13:00 | 27/10/2019 13:00 |
| Last date & time for Tender/Proposal Security Submission | 21/10/2019 12:00 | 27/10/2019 12:00 |
| Closing Date & Time | 21/10/2019 13:00 | 27/10/2019 13:00 |
| Brief Description of Goods,Works or Service | 1.Improvement of Bordail to Chowtail road by BC at Ch.00-2070m[Road ID 32645072] under Dhamrai Upazila, Dist: Dhaka.2.Improvement of Shitakali bazar to Barigaw road by BC at Ch.00-450m[Road ID 326145058] under Dhamrai Upazila, Dist: Dhaka. Salvage amount:11,51,465.00 Package No- GDP-IV/DHK/DHAM/W(R)-255 |
1.Improvement of Bordail to Chowtail road by BC at Ch.00-2070m[Road ID 32645072] under Dhamrai Upazila, Dist: Dhaka.2.Improvement of Shitakali bazar to Barigaw road by BC at Ch.00-450m[Road ID 326145058] under Dhamrai Upazila, Dist: Dhaka. Salvage amount:11,51,465.00 Package No- GDP-IV/DHK/DHAM/W(R)-255 |