View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Please follow the new modified date and time. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 20/04/2020 16:00 | 13/05/2020 16:00 |
| Opening Date & Time | 21/04/2020 14:00 | 14/05/2020 14:00 |
| Last date & time for Tender/Proposal Security Submission | 21/04/2020 13:00 | 14/05/2020 13:00 |
| Start Date(Lot No : 1) | 05/05/2020 | 04/06/2020 |
| Closing Date & Time | 21/04/2020 14:00 | 14/05/2020 14:00 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Please follow the allocated date and time. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 05/04/2020 16:00 | 20/04/2020 16:00 |
| Eligibility of Consultant |
The minimum number of years of general experience of the Tenderer in the construction or renovation works as Prime Contractor or Management Contractor shall be 5 (Five) years. Tenderer should have valid Trade license, VAT certificate, TIN certificate etc
The required average annual construction turnover shall be at least Tk 20,50,00,000.00 (Taka twenty two Crore fifty lac Only) over the best 3 (three) years in the last 5 (Five) years. Special Instruction: In case of credit line, Specific Format which is attached in Section: 8 (Particular Specifications), must be used. Technical Specifications are also attached in Section 8 (Particular Specifications). Only for system requirement, you are requested to quote unit price in e-PW3, Section 6, Form Name- "Schedule of Day Works" . For example, unit price is 0.001. Once it is quoted will not be considered in total quoted amount. |
The minimum number of years of general experience of the Tenderer in the construction or renovation works as Prime Contractor or Management Contractor shall be 5 (Five) years. Tenderer should have valid Trade license, VAT certificate, TIN certificate etc
The required average annual construction turnover shall be at least Tk 20,50,00,000.00 (Taka twenty two Crore fifty lac Only) over the best 3 (three) years in the last 5 (Five) years. Special Instruction: In case of credit line, Specific Format which is attached in Section: 8 (Particular Specifications), must be used. Technical Specifications are also attached in Section 8 (Particular Specifications). Only for system requirement, you are requested to quote unit price in e-PW3, Section 6, Form Name- "Schedule of Day Works" . For example, unit price is 0.001. Once it is quoted will not be considered in total quoted amount. |
| Opening Date & Time | 06/04/2020 14:00 | 21/04/2020 14:00 |
| Last date & time for Tender/Proposal Security Submission | 06/04/2020 13:00 | 21/04/2020 13:00 |
| Closing Date & Time | 06/04/2020 14:00 | 21/04/2020 14:00 |
| Brief Description of Goods,Works or Service |
|
|