View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | Amendment Tender document |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--B. Time Control-- | The Contractor shall submit a Programme for the Works within 07 (Seven) days from signing of Contract Agreement. If the contractor failed to submit programme of works then Tk. 25,000.00( Twenty five thousand) only will be heldup from each progressive payment. |
The Contractor shall submit a Programme for the Works within 07 (Seven) days from signing of Contract Agreement. If the contractor failed to submit programme of works then Tk. 25,000.00( Twenty five thousand only) will be held up from each progressive payment. |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works of the official estimated cost of the uncompleted works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works. |
| PCC--F. Termination-- |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 (Ten) percent. |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 (Ten) percent of the official estimated cost of the uncompleted works. |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Amendment the Tender document. |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date; within 07 (Seven) days after signing of the contract. |
Possession of the Site to the Contractor shall be given on the following date; within 07 (Seven) days after signing of Contract Agreement. |
| PCC--B. Time Control-- | The Intended Completion Date for the whole of the Works shall be120 ( One Hundred Twenty ) days form signing of Contract Agreement. |
The Intended Completion Date for the whole of the Works shall be120 ( One Hundred Twenty ) days from signing of Contract Agreement. |
| PCC--B. Time Control-- | The Contractor shall submit a Programme for the Works within 05 (Five) days form signing of Contract Agreement. |
The Contractor shall submit a Programme for the Works within 07 (Seven) days from signing of Contract Agreement. If the contractor failed to submit programme of works then Tk. 25,000.00( Twenty five thousand) only will be heldup from each progressive payment. |
| PCC--D. Cost Control-- | The proportion of payments to be retained is: 10 (Ten) percent of the contract price. a) 5% of the total contract price Pay order/Bank gurantee will be submitted by the successfull bidder as performance security. b) 5% will be retained as retention money from each progressive payment. (After successfull completion of the whole works 5% performance security will refunded to the contractor) |
The proportion of payments to be retained is: 10 (Ten) percent of the contract price. a) 5% of the total contract price Pay order/Bank gurantee will be submitted by the successfull bidder as performance security. b) 5% will be retained as retention money from each progressive payment. (After successfull completion of the whole works 5% performance security will be refunded to the contractor) |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works of the official estimated cost of the uncompleted works. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk. 38.00 (Thirty Eight ) lakh over the last 05 (Five) years. |
The required average annual construction turnover shall be greater than Tk. 55.00 ( Fifty Five ) lakh over the last 05 (Five) years. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Tender document |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As stated in the Tender Docuemnt. |
As stated in the Tender Docuemnt. |
| Brief Description of Goods,Works or Service | At Chattogram Railway Station- Repairs to damaged road surface leading from station road to GRP office and connecting road of old station to new station including construction of footpath including other ancillary works as per approved drawing. |
At Chattogram Railway Station- Repairs to damaged road surface leading from station road to GRP office and connecting road of old station to new station including construction of footpath including other ancillary works as per approved drawing. |