View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Document |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--B. Time Control-- | The Intended Completion Date for the whole of the Works shall be 3 (Six) months from the contract signing |
The Intended Completion Date for the whole of the Works shall be 3 (Three) months from the contract signing |
| TDS/PDS--E. e-Tender Submission-- | The deadline for lodgment of e-Tenders is 20-Sep;-2019 12:00 Noon. |
The deadline for lodgment of e-Tenders is 20-Oct-2019 12:00 Noon. |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Document |
| Field Name | Old Value | New Value | ||||
|---|---|---|---|---|---|---|
| PCC--A. General-- |
The Project Manager is |
The Project Manager is AE, Narayanganj Zila Parishod |
||||
| PCC--A. General-- |
The Works consist of |
The Works consist of: a. Repair of Road from Sonacora H/O Nurul Haque to H/O Kaium Member Under Bandar Upazila Dist- Narayanganj. b. Field Raising of Hazi Abdul Ali Juhur Ali Stadium Field at Cunavurasto Under Bandar Upazila Dist- Narayanganj. |
||||
| PCC--A. General-- |
The Procuring Entity is |
The Procuring Entity is Chief Executive Officer, Narayanganj Zila Parishod, Narayanganj. |
||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at upazila Bandar |
||||
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are: Not Applicable |
||||
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date;
[state date of possession of site] |
Possession of the Site to the Contractor shall be given on the following date: Not Applicable |
||||
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
Possession of the Site to the Contractor shall be given on the following date; Not Applicable |
||||
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Start Date shall be within 7 (seven) days of contract signing |
||||
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Intended Completion Date for the whole of the Works shall be 3 (Six) months from the contract signing |
||||
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is twelve (12) months |
||||
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
The following additional events shall also be the Compensation Events: Not Applicable |
||||
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10% (Ten percent) of the final Contract price of the whole of the Works. |
||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 5% (Five percent) of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
||||
| PCC--F. Termination -- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is (10%) ten percent. |
||||
| PCC--G. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below: The Presedent of IEB |
||||
| TDS/PDS--A. General-- |
|
|
||||
| TDS/PDS--A. General-- | Only Enlisted Contractors of the categories (nature of business) [state the categories] are eligible. |
Only Enlisted Contractors are eligible. And Must Uploded Zilaparishad Enlisted Copy |
||||
| TDS/PDS--B. Tender Document-- | Allowed to post clarification till [Date and Time] |
Allowed to post clarification till : Not Applicable |
||||
| TDS/PDS--C. Qualification Criteria-- |
The essential equipment required [List of the equipments] Or
Not Applicable (delete as appropriate) |
The essential equipment required [List of the equipments] |
||||
| TDS/PDS--C. Qualification Criteria-- |
The Key Personnel required [list of the key personnel] Not Applicable (delete as appropriate)
|
The Key Personnel required [list of the key personnel] |
||||
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
|
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 2,00,000.00 ( Two Lakh only) |
||||
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents: |
Tenderer shall submit with its Tender, the following : Additional supporting documents are (i) valid trade licence, (Update) (ii) up to date VAT clearance certificate, (iii)valid TIN certificate, etc.(Update) (iv)Enlisted Book, etc. |
||||
| TDS/PDS--D. Tender Preparation-- | The Tender Validity period shall be [state number] days.
[normally 60 to 90 days deemed reasonable] |
The Tender Validity period shall be 90 days. |
||||
| TDS/PDS--D. Tender Preparation-- |
Tender Security shall be [required ] or [not required] |
The amount of the Tender Security shall be Tk. 22,500.00 (Twenty Two Thousand Five Hundred) Only. |
||||
| TDS/PDS--E. e-Tender Submission-- |
The deadline for lodgment of e-Tenders is [state time, and identify AM or PM e.g 10.30 a.m] |
The deadline for lodgment of e-Tenders is 20-Sep;-2019 12:00 Noon. |
||||
| TDS/PDS--G. e-Contract Award-- | The amount of Performance Security shall be [state percentage] percent of the Contract Price.
[Three (3) percent to Five (5) percent of the Contract price] |
The amount of Performance Security shall be 5 (Five) percent of the Contract Price. |