View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Local Government, Rural Development and Co-operatives Division : Local Government Division
Organization : Department of Public Health Engineering (DPHE) Procuring Entity Name : Office of the Executive Engineer DPHE, Kurigram
Procuring Entity Code : Procuring Entity District : Kurigram
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : 46.03.2600.000.07.001.18-441 Date:13/03/2019 Tender/Proposal Status :
App ID : 159685 Tender/Proposal ID : 375439
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government, Aid or Grant Development Partner : Islamic Development Bank
Particular Information :
Project Code : 224132700 Project Name : Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GOB-IDB)
Tender/Proposal Package No. and Description : KUR.-W-18
Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AEs Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh GoB-IDBFY 2019-2020
Category : Construction work; Miscellaneous services;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator;Washing and dry-cleaning services;Laundry-collection services;Textile-cleaning services;Fur-products cleaning services;Colouring services;Pressing services;Dyeing services;Hairdressing and beauty treatment services;Hairdressing services;Beauty treatment services;Physical well-being services;Turkish bath services;Spa services;Massage services;Accommodation and office services;Accommodation services;Civic-amenity services;Car-park management services;Marine services;Aquatic marine services;Port management services;Diving services;Funeral and related services;Funeral services;Miscellaneous services n.e.c.;Decommissioning services;Relocation services;Tailoring services;Upholstering services;Locksmith services
Scheduled Tender/Proposal Publication
Date and Time :
28-Oct-2019 22:15 Tender/Proposal Document last selling /
downloading Date and Time :
12-Nov-2019 20:00
Pre - Tender/Proposal meeting Start
Date and Time :
29-Oct-2019 10:15 Pre - Tender/Proposal meeting End
Date and Time :
05-Nov-2019 10:15
Tender/Proposal Closing
Date and Time :
13-Nov-2019 12:15 Tender/Proposal Opening
Date and Time :
13-Nov-2019 12:15
Last Date and Time for Tender/Proposal Security
Submission :
13-Nov-2019 11:15    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

All tenderers in Bangladesh registered in National e-GP System, who fulfills the qualification criteria as specified in the Tender Data Sheet (TDS) of the Tender Document.
Note:
a. The tenderer must submit up to date authorization letter for submission against this tender ID.
b. Tenderer should mention the full name of his/her firm (No abbreviation is allowed).
c. The Rules, Regulation & Acts (including all amendments) of "The Public procurement Regulation 2008" must be applied on contractors.
d. Any type of apathy/negligence/delay of execution of work will cost the winning bidder a penalty of minimum 3 years debars in respective zone.
e. Similar experience is must.
f. All other information is in Tender Data Sheet (TDS).
g. 10% Above or Less is Applicable as per Govt. Order(GO)/PPR.
h. Test of materials must be perform under BUET/RUET/DUET/Equivalent and test of water samples must be perform from Zonal Laboratory of DPHE. Tenderer Should bear all cost of Tests.
i. Procuring Entity (PE) reserve the rights to subtract, modify and cancel the whole tender procedure without showing any reason.

Brief Description of Works :

Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AE Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GoB-IDB)(FY: 2018-2019)

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 1500
Mode of Payment :
Tender/Proposal Security Valid Up to : 10-Mar-2020
Tender/Proposal Valid Up to : 11-Feb-2020
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
01 Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AEs Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh GoB-IDBFY 2019-2020 Kurigram 95000 14-Nov-2019 15-Jun-2020
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : PE Kurigram Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: Office of the Executive Engineer DPHE, Kurigram
City: Kurigram
Thana: Kurigram
District: Kurigram - 5600
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 05-8161515
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Corrigendum-01

Field Name Old Value New Value
Eligibility of Consultant

All tenderers in Bangladesh registered in National e-GP System, who fulfills the qualification criteria as specified in the Tender Data Sheet (TDS) of the Tender Document.
Note:
a. The tenderer must submit up to date authorization letter for submission against this tender ID.
b. Tenderer should mention the full name of his/her firm (No abbreviation is allowed).
c. The Rules, Regulation & Acts (including all amendments) of "The Public procurement Regulation 2008" must be applied on contractors.
d. Any type of apathy/negligence/delay of execution of work will cost the winning bidder a penalty of minimum 3 years debars in respective zone.
e. Similar experience is must.
f. All other information is in Tender Data Sheet (TDS).
g. 10% Above or Less is Applicable as per Govt. Order(GO)/PPR.
h. Test of materials must be perform under BUET/RUET/DUET/Equivalent and test of water samples must be perform from Zonal Laboratory of DPHE. Tenderer Should bear all cost of Tests.
i. Procuring Entity (PE) reserve the rights to subtract, modify and cancel the whole tender procedure without showing any reason.

All tenderers in Bangladesh registered in National e-GP System, who fulfills the qualification criteria as specified in the Tender Data Sheet (TDS) of the Tender Document.
Note:
a. The tenderer must submit up to date authorization letter for submission against this tender ID.
b. Tenderer should mention the full name of his/her firm (No abbreviation is allowed).
c. The Rules, Regulation & Acts (including all amendments) of "The Public procurement Regulation 2008" must be applied on contractors.
d. Any type of apathy/negligence/delay of execution of work will cost the winning bidder a penalty of minimum 3 years debars in respective zone.
e. Similar experience is must.
f. All other information is in Tender Data Sheet (TDS).
g. 10% Above or Less is Applicable as per Govt. Order(GO)/PPR.
h. Test of materials must be perform under BUET/RUET/DUET/Equivalent and test of water samples must be perform from Zonal Laboratory of DPHE. Tenderer Should bear all cost of Tests.
i. Procuring Entity (PE) reserve the rights to subtract, modify and cancel the whole tender procedure without showing any reason.

PCC--A. General--

The Works consist of
[state brief summary]
 

The Works consist of Civil, installation & Running water supply etc
 

PCC--A. General--

The Procuring Entity is
[Name, address]
 

 

The PE is

Engr. Md. Shayhan Ali

Executive Engineer

DPHE, Kurigram.

Phone No.: 058161515

PCC--A. General--

The Site is located at [location] and is defined in drawings No:
[insert numbers]
 

 

The Site is located at Kurigram District.Location & Position depends on Procuring Entity (PE). No objection will grant for this purpose.

PCC--A. General--

The Project Manager is
[Name, address]
 

 

The Project Manager is
N/A
 

PCC--A. General--

Other documents forming part of the Contract are;

[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]
 

Other documents forming part of the Contract are;
1) General Specification (uploaded in section 7: General Specifications/collect form PE office)
2) Special Conditions of Tender & Contract (uploaded in section 8: Particular Specifications/collect form PE office)

PCC--A. General--

Possession of the Site to the Contractor shall be given on the following date;

[state date of possession of site]
 

Possession of the Site or part(s) of the Site Within 05 (Five) days from the date of contract signing.

PCC--B. Time Control--

The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract]
 

Commencement Date of Works shall be as follows;

 

The start date shall be within 05 (Five) days from the date of contract signing.

PCC--B. Time Control--

The Intended Completion Date for the whole of the Works shall be [insert date]
[to be calculated from the start Date]
 

The Intended Completion Date for the whole of the Works shall be 180 days.

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually ten (10) days or may be less]
 

The Contractor shall submit a Programme for the Works within ten (10) days of signing the Contract.
 

PCC--C. Quality Control--

The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is 12 month.

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:
[list events or state none ]
 

The following additional events shall also be the Compensation Events: none.

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.

 

The proportion of payments to be retained is 10 (Ten) percent from each progressive payment & also from final account (Total final billed amount).i.e. Retention money is to be retained total
10 % from total final billed amount.

PCC--D. Cost Control--

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]
 

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works.
 

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay]
Guide to application of GCC Sub Clause 28.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x P x n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price.
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay of the final Contract price of the uncompleted Works or any part there of.
n = No of days of delay for completion of works under the Contract]
 

he amount of Liquidated Damages or in other words Delay Damages is 0.05 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay.

PCC--F. Termination--

The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

 

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 10 percent.

PCC--H. Disputes and Settlement--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]
 

The arbitration shall be conducted in the place mentioned below:
DPHE Bhaban
14, Shahid Captain Monsur Ali Sarani, Kakrail, Dhaka-1000, Bangladesh

TDS/PDS--A. General--

 

The PE is [state name of PE]

 

 

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:
Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

 

The PE is

Engr. Md. Shayhan Ali

Executive Engineer

DPHE, Kurigram.

Phone No.: 058161515

 

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:
Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

TDS/PDS--B. Tender Document--

Allowed to post clarification till [Date and Time]

 

Post clarification is not allowed.

TDS/PDS--C. Qualification Criteria--

The minimum amount of liquid assets or working capital or credit facilities of the  Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:
Contract Value:   Tk 24 lakh
Contract period:   12 months
Assuming work time:  1 month
Invoice period:    0.5 month
Certification Time:   0.5 month
Contingency Time:   1 month

Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 12.00 Lac.

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
 

The minimum capacity shall be: 25 Lakh


The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction  turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be  best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)]
Example:
Estimated Contract Value:  Tk 24 lakh
Contract period:   12 months
Estimated Annual Cash Flow:  Tk 24 lakh
Required average annual construction turn over: Tk 12 lakh, using a multiplier of 0.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The required average annual construction turnover shall be greater than Tk. 25.00 lakh/year over the last 05 years.

TDS/PDS--C. Qualification Criteria--

A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required.

[the minimum value of the similar works under a single or multiple number of  contract(s) is recommended to be between 50  and 75 percent of the estimated cost, rounded off to nearest Taka  thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]

[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package]
 

 

A satisfactory completion of similar works of at least Tk. 20.00 lakh under (01) singal of contract(s) over a period of 05 years shall be required.

TDS/PDS--D. Tender Preparation--

Tenderer shall submit with its Tender, the following additional documents:

Tenderer shall submit with its Tender, the following additional documents:

1. Valid trade licence.

2. Worke/Expericence Certificate.

3. Bank Solvency Certificate.

4. TIN Certificate.

5. VAT & IT Certificate.

TDS/PDS--D. Tender Preparation--

The Tender Validity period shall be [state number] days.

[normally 60 to 90 days deemed reasonable]
 

The Tender Validity period shall be 90 days.

TDS/PDS--D. Tender Preparation--

The amount of the Tender Security shall be [ state amount ]
[note: Not exceeding three percent (3%) of the official estimated cost but as a fixed amount] 

 

 

The amount of the Tender Security shall be : As per Notice/TDS.
 

TDS/PDS--E. e-Tender Submission--

The deadline for lodgment of e-Tenders is [state time, and identify AM or PM e.g 10.30 a.m]
[state date, e.g 15 June,2011  ].
 

he deadline for lodgment of e-Tenders is As per Notice/TDS.

Brief Description of Goods,Works or Service

Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AE Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GoB-IDB)(FY: 2018-2019)

Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AE Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GoB-IDB)(FY: 2018-2019)

 
Save As PDF