View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Corrigendum-01 |
| Field Name | Old Value | New Value | ||||
|---|---|---|---|---|---|---|
| Eligibility of Consultant | All tenderers in Bangladesh registered in National e-GP System, who fulfills the qualification criteria as specified in the Tender Data Sheet (TDS) of the Tender Document. |
All tenderers in Bangladesh registered in National e-GP System, who fulfills the qualification criteria as specified in the Tender Data Sheet (TDS) of the Tender Document. |
||||
| PCC--A. General-- |
The Works consist of |
The Works consist of Civil, installation & Running water supply etc |
||||
| PCC--A. General-- |
The Procuring Entity is |
The PE is Engr. Md. Shayhan Ali Executive Engineer DPHE, Kurigram. Phone No.: 058161515 |
||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at Kurigram District.Location & Position depends on Procuring Entity (PE). No objection will grant for this purpose. |
||||
| PCC--A. General-- |
The Project Manager is |
The Project Manager is |
||||
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; |
||||
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date;
[state date of possession of site] |
Possession of the Site or part(s) of the Site Within 05 (Five) days from the date of contract signing. |
||||
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
Commencement Date of Works shall be as follows;
The start date shall be within 05 (Five) days from the date of contract signing. |
||||
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be 180 days. |
||||
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programme for the Works within ten (10) days of signing the Contract. |
||||
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is 12 month. |
||||
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
The following additional events shall also be the Compensation Events: none. |
||||
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is 10 (Ten) percent from each progressive payment & also from final account (Total final billed amount).i.e. Retention money is to be retained total |
||||
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
he amount of Liquidated Damages or in other words Delay Damages is 0.05 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
||||
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 10 percent. |
||||
| PCC--H. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below: |
||||
| TDS/PDS--A. General-- |
|
|
||||
| TDS/PDS--B. Tender Document-- | Allowed to post clarification till [Date and Time] |
Post clarification is not allowed. |
||||
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.] |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 12.00 Lac. |
||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum capacity shall be:[70%-80% of the official estimated cost]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package |
The minimum capacity shall be: 25 Lakh
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package |
||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)] |
The required average annual construction turnover shall be greater than Tk. 25.00 lakh/year over the last 05 years. |
||||
| TDS/PDS--C. Qualification Criteria-- | A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required. [the minimum value of the similar works under a single or multiple number of contract(s) is recommended to be between 50 and 75 percent of the estimated cost, rounded off to nearest Taka thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package] |
A satisfactory completion of similar works of at least Tk. 20.00 lakh under (01) singal of contract(s) over a period of 05 years shall be required. |
||||
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents: |
Tenderer shall submit with its Tender, the following additional documents: 1. Valid trade licence. 2. Worke/Expericence Certificate. 3. Bank Solvency Certificate. 4. TIN Certificate. 5. VAT & IT Certificate. |
||||
| TDS/PDS--D. Tender Preparation-- | The Tender Validity period shall be [state number] days.
[normally 60 to 90 days deemed reasonable] |
The Tender Validity period shall be 90 days. |
||||
| TDS/PDS--D. Tender Preparation-- |
The amount of the Tender Security shall be [ state amount ] |
The amount of the Tender Security shall be : As per Notice/TDS. |
||||
| TDS/PDS--E. e-Tender Submission-- |
The deadline for lodgment of e-Tenders is [state time, and identify AM or PM e.g 10.30 a.m] |
he deadline for lodgment of e-Tenders is As per Notice/TDS. |
||||
| Brief Description of Goods,Works or Service | Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AE Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GoB-IDB)(FY: 2018-2019) |
Up-gradation of Existing DPHE Office to Accommodate Office of the newly created AE Office at Ulipur Upazila in Kurigram District under Urban Water Supply and Sanitation in 23 Pourashavas Project in Bangladesh (GoB-IDB)(FY: 2018-2019) |