As per TDS
- Contractor will be disqualified, if his total quoted amount in BOQ is more than 10% less or more than 10% high of official estimated cost according to latest ammendment of PPR- 2008.
Drilling and installation of 06 Six Nos 50mm dia Test Tubewell 04 Nos production well Construction of 04 Nos pump house Supplying & Installation of 04 Nos Submersible Pump Motor set with accessories electrical works & Reservior and Construction of Pumping Station and other Ancillary Works Civil Electrical & Mechanical works at kajulia Gopalganj Under Gopalganj and Bagerhat Pourashava Water Supply & Environmental Sanitation System Improvement Project FY- 2019- 2020.