View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Documents |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As per Bidding Documents. |
As per Bidding Documents. |
| PCC--A. General-- |
The Project Manager is |
The Project Manager is |
| PCC--A. General-- |
The Start Date shall be Date: As Per Tender Notice. |
The Start Date shall be within 7(seven) days from the date of signing of contract. |
| PCC--A. General-- |
The PE is |
The PE is |
| PCC--A. General-- | The original Contract price is : As Per NoA |
The original Contract price is the same as total quoted price at BOQ. |
| PCC--A. General-- |
The Works consist of GPS Building Work etc. |
The Works consist of section:
{ Conostruction of School building & Supply of furniture. ( as per Specification, BOQ and Drawings)} |
| PCC--A. General-- |
Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor; |
Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor; 2. Quality Control Engineer ( Diploma in civil Engg).
3. Works Supervisor ( H.S.S) |
| PCC--A. General-- | Nominated Subcontractor(s) named below : Not Applicable |
Nominated Subcontractor(s) named below Shall be entitled to execute the following specific components of the Work: Not applicable. |
| PCC--A. General-- |
The Contractual matters between the PE and the Contractor shall be decided by |
The Contractual matters between the PE and the Contractor shall be decided by Chief Engineer. |
| PCC--A. General-- |
Other documents forming part of the Contract are; |
Other documents forming part of the Contract are;
ii) Work Propgram 1. The following environmental clauses will be included in the bidding document of the subprojects:
The contractor will erect sufficient number of temporary sanitary toilets and shelter both for male and female workers at the site with proper sanitation system. 2. In addition, the contractor should follow environment management plan (EMP) of the subproject including ECP-11 (Appendix-6) |
| PCC--B. Time Control-- |
Commencement Date of Works shall be as follows; |
Commencement Date of Works shall be as follows; |
| PCC--B. Time Control-- |
The period between Programme updates is quarterly |
The period between Programme updates is 90 ( Ninety) days |
| PCC--D. Cost Control-- |
The proportion of payments to be retained is five (05) percent. |
The proportion of payments to be retained is 5% (Five percent) fo each payment . |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.075(Zero point zero seven five) percent of its Contract price per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.05(Zero point zero five) percent of its Contract price per day of delay. |
| PCC--D. Cost Control-- |
The Bonus for the whole of the Works is â??Not Applicableâ?�. |
The Bonus for the whole of the Works is [insert percentage] percent of the final contract price per day. |
| PCC--D. Cost Control-- |
The Advance Payment:None |
The Advance Payment shall be [insert percentage] and shall be paid to be the Contractor not later than [insert date] :Not Applicable. |
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the PEâ??s additional cost for completing the uncompleted Works, is ten (10) percent. |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 15 ( Fifteen) percent. |
| PCC--G. Claims, Disputes and Arbitration-- |
The Adjudicator jointly appointed by the parties is: |
The Adjudicator jointly appointed by the parties is: |
| TDS/PDS--A. General-- |
The PE is |
The PE is
Tender Package No: e-Tender/PEDP4/CTG/CIT/2019-20/W17.00346 |
| TDS/PDS--A. General-- |
The name of the Development Partner is N/A |
The name of the Development Partner is : WB, ADB, UNICF, JICA & EU |
| TDS/PDS--A. General-- |
The source of public funds is GoB |
The source of public funds is :GoB & DPs |
| TDS/PDS--B. e-Tender Document (e-TD)-- |
Pre- Tender Meeting : As Per Tender Notice. |
Pre- Tender Meeting :
i) Start Time & Date : 10.00 am, 30-Jan-2020 |
| TDS/PDS--C. Qualification Criteria-- |
The Nominated Subcontractor(s) : Not Applicable. |
The Nominated Subcontractor(s) named insert name (s)] shall execute the following specific components of the proposed Works: None |
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its Tender the following additional documents:
1. Updated Trade License. |
25.1 The Tender prepared by the Tenderer shall comprise the following: (a) the Tender Submission Letter (Form e-PW3-1) as furnished in Section 5: e-Tender Forms;
(b) Tenderer Information (Form e-PW3-2) as furnished in Section 5: e-Tender Forms;
(c) the priced Bill of Quantities for each lot in accordance with ITT Clauses 26 and 27;
(d) Tender Security as stated under ITT Clauses 34 and 35. (e) Written confirmation authorizing the signatory of the Tenderer including National ID to submit the e-Tender, as stated under ITT Sub Clause 39.4; (f) Valid Trade license to be mapped from e-GP Common document library of the Tenderer ; (g) Documentary evidence of Tax Identification Number (TIN) and Value Added Tax (VAT) as a proof of taxation obligations as stated under ITT Sub Clause 5.10 to be mapped from e-GP Common document library of the Tenderer; (h) Technical Proposal describing work plan & method, personnel, equipment and schedules as stated under ITT Clause 30; (i) documentary evidence as stated under ITT Clause 28 and 31 establishing the Tenderer’s eligibility and the minimum qualifications of the Tenderer required to be met for due performance of the Works and physical services under the Contract; (j) Documents establishing legal and financial autonomy and compliance with commercial law, as stated under ITT Sub-clause 5.4 in case of government owned entity; and (k) any other document as specified in the TDS. |
| TDS/PDS--E. Tender e-Submission-- | The deadline for lodgement of e-Tenders is: As Per Tender Notice. |
The deadline for lodgement of e-Tenders is: Time & Date : up to 12.50am, 13-02-2020 |
| TDS/PDS--G. Contract Award-- |
The amount of Performance Security shall be 10% of the Contract Price. |
The amount of Performance Security shall be 5% of the Contract Price. |
| Brief Description of Goods,Works or Service | e-Tender/PEDP4/CTG/CIT/2019-20/W17.00346 |
e-Tender/PEDP4/CTG/CIT/2019-20/W17.00346 |