View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Tender security Submission Time and BOQ changed due to unavoidable situation. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 25/01/2016 17:00 | 03/02/2016 17:00 |
| Opening Date & Time | 26/01/2016 14:00 | 04/02/2016 14:00 |
| Last date & time for Tender/Proposal Security Submission | 18/01/2016 11:53 | 04/02/2016 12:00 |
| Closing Date & Time | 26/01/2016 13:30 | 04/02/2016 13:30 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | BOQ |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 17/01/2016 17:00 | 25/01/2016 17:00 |
| Opening Date & Time | 18/01/2016 14:00 | 26/01/2016 14:00 |
| Meeting End Date & Time | 03/01/2016 17:00 | 24/01/2016 17:00 |
| Meeting Start Date & Time | 30/12/2015 14:00 | 19/01/2016 11:00 |
| Closing Date & Time | 18/01/2016 13:30 | 26/01/2016 13:30 |
| TDS/PDS--C. Qualification Criteria-- |
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit line of theTenderer shall be Tk[3100000.00(thurty one lakh)]
|
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit line of theTenderer shall be Tk[3100000.00(thurty one lakh)]
|
| TDS/PDS--C. Qualification Criteria-- |
A satisfactory completion of similar works of at least Tk[3700000.00(Thirty seven lakh] under [01(One)] number of contract(BC Road) over a period of last 5 (five) years shall be required.(not before FY: 2010-11)-
|
The required average annual construction turnover shall be greater than Tk[3700000.00(Thurtyseven lakh) Last 5(five) years. (not before FY: 2010-11)- |
| TDS/PDS--C. Qualification Criteria-- |
A satisfactory completion of similar works of at least Tk[6100000.00(sixty one lakh] under [01(One)] number of contract over a period of last 5 (five) years shall be required.(not before FY: 2010-11)-
|
A satisfactory completion of similar works of at least Tk[5000000.00(Fifty lakh] under [01(One)] number of contract over a period of last 5 (five) years shall be required.(not before FY: 2010-11)-
|
| Tender/Proposal Security (Amount in BDT)(Lot No : 01) | 310000.0 | 250000 |