View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Amendment on Tender selling last date, Tender security selling last date, Tender closing date and opening date |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 28/11/2021 | 09/12/2021 |
| Document last selling date & time | 10/05/2020 16:00 | 01/06/2020 16:00 |
| Opening Date & Time | 11/05/2020 12:30 | 02/06/2020 12:30 |
| PCC--A. General-- | The Start Date shall be 28-May-2020. |
The Start Date shall be 10-June-2020. |
| PCC--A. General-- | The Sectional Completion Dates are: 27-Nov-2021. |
The Sectional Completion Dates are: 09-Dec-2021. |
| Last date & time for Tender/Proposal Security Submission | 10/05/2020 16:00 | 01/06/2020 16:00 |
| Start Date(Lot No : 1) | 28/05/2020 | 10/06/2020 |
| Closing Date & Time | 11/05/2020 12:30 | 02/06/2020 12:30 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Amendment on Tender selling last date, Tender security selling last date, Tender closing date and opening date |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 27/10/2021 | 28/11/2021 |
| Document last selling date & time | 19/04/2020 16:00 | 10/05/2020 16:00 |
| Eligibility of Consultant | i) As Per Tender Document. |
i) As Per Tender Document. |
| Opening Date & Time | 20/04/2020 12:30 | 11/05/2020 12:30 |
| PCC--A. General-- | The Start Date shall be 28-Apr-2020. |
The Start Date shall be 28-May-2020. |
| PCC--A. General-- | The Sectional Completion Dates are: 27-Oct-2021. |
The Sectional Completion Dates are: 27-Nov-2021. |
| Last date & time for Tender/Proposal Security Submission | 19/04/2020 16:00 | 10/05/2020 16:00 |
| Start Date(Lot No : 1) | 28/04/2020 | 28/05/2020 |
| Closing Date & Time | 20/04/2020 12:30 | 11/05/2020 12:30 |
| Brief Description of Goods,Works or Service | Construction of staff hostel building up to 1st floor with 6-storied foundation at Training Academy Coxsbazar. |
Construction of staff hostel building up to 1st floor with 6-storied foundation at Training Academy Coxsbazar. |