Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | At Notice: |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 01) | 30/08/2020 | 24/09/2020 |
| Document last selling date & time | 01/04/2020 17:00 | 07/04/2020 17:00 |
| Opening Date & Time | 02/04/2020 12:15 | 08/04/2020 12:15 |
| Meeting End Date & Time | 31/03/2020 13:00 | 06/04/2020 13:00 |
| Last date & time for Tender/Proposal Security Submission | 02/04/2020 11:45 | 08/04/2020 11:45 |
| Start Date(Lot No : 01) | 22/04/2020 | 07/05/2020 |
| Closing Date & Time | 02/04/2020 12:15 | 08/04/2020 12:15 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | 1. At TDS :C. Qualification Criteria
2. At BOQ: a) item no :22 & 24 |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 01) | 25/08/2020 | 30/08/2020 |
| Document last selling date & time | 25/03/2020 17:00 | 01/04/2020 17:00 |
| Eligibility of Consultant | As Per TDS . |
As Per TDS . |
| Opening Date & Time | 29/03/2020 12:15 | 02/04/2020 12:15 |
| Meeting End Date & Time | 24/03/2020 13:00 | 31/03/2020 13:00 |
| Last date & time for Tender/Proposal Security Submission | 29/03/2020 11:45 | 02/04/2020 11:45 |
| Start Date(Lot No : 01) | 19/04/2020 | 22/04/2020 |
| Closing Date & Time | 29/03/2020 12:15 | 02/04/2020 12:15 |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk 1,65,00,000(One Crore and Sixty Five Lakhs) over the last 03(Three) years.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The required average annual construction turnover shall be greater than Tk 1,65,00,000(One Crore and Sixty Five Lakhs) over the last 03(Three) years.
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 60,00,000(Sixty Lakhs) . |
| TDS/PDS--C. Qualification Criteria-- | The minimum capacity shall be: 90,00,000(Ninety Lakhs) .
[70%-80% of the official estimated cost]
Where
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
The minimum capacity shall be: 90,00,000(Ninety Lakhs) . |
| Brief Description of Goods,Works or Service | Installations of 100 x 50 mm dia. 39Thirty Nine nos deep tube well with submersible pump capacity 1.5 HP with RO filter at different primary schools of Sadar Upazilla Bhola District under PEDP-4 |
Installations of 100 x 50 mm dia. 39Thirty Nine nos deep tube well with submersible pump capacity 1.5 HP with RO filter at different primary schools of Sadar Upazilla Bhola District under PEDP-4 |