View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 3
|
|
| Amendment / Corrigendum Text : | Time extension due to holiday. |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 01) | 03/08/2020 | 20/08/2020 |
| Document last selling date & time | 15/04/2020 17:00 | 03/05/2020 17:00 |
| Opening Date & Time | 16/04/2020 15:00 | 04/05/2020 15:00 |
| Meeting End Date & Time | 13/04/2020 17:00 | 27/04/2020 17:00 |
| Last date & time for Tender/Proposal Security Submission | 16/04/2020 12:00 | 04/05/2020 12:00 |
| Start Date(Lot No : 01) | 03/05/2020 | 20/05/2020 |
| Closing Date & Time | 16/04/2020 15:00 | 04/05/2020 15:00 |
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Time extension due to holiday. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 07/04/2020 17:00 | 15/04/2020 17:00 |
| Opening Date & Time | 08/04/2020 15:00 | 16/04/2020 15:00 |
| Meeting End Date & Time | 05/04/2020 17:00 | 13/04/2020 17:00 |
| Last date & time for Tender/Proposal Security Submission | 08/04/2020 12:00 | 16/04/2020 12:00 |
| Closing Date & Time | 08/04/2020 15:00 | 16/04/2020 15:00 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Time extension due to holiday. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 01/04/2020 17:00 | 07/04/2020 17:00 |
| Eligibility of Consultant | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five) years. (a) The minimum specific experience as a Prime Contractor in construction works of at least 01(one) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 05 (Five) years, each with a value of at least Tk. 65,00,000.00 Financial Year: 2014-2015, 2015-2016, 2016-2017, 2017-2018, 2018-2019. (b) The required average annual construction turnover shall be greater than Tk. 6,00,00,000.00 over the last five (5) years. Only Payment certificate or Income Tax Certificate from National Board of Revenue will be consider as annual construction turnover.
Tenderers having quoted the tender price more than 10 (Ten) percent above or below the official cost estimate, the tender will be rejected as per ITT Clause 30.3 |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five) years.
(a) The minimum specific experience as a Prime Contractor in construction works of at least 01(one) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 05 (Five) years, each with a value of at least Tk. 65,00,000.00 Financial Year: 2014-2015, 2015-2016, 2016-2017, 2017-2018, 2018-2019. (b) The required average annual construction turnover shall be greater than Tk. 6,00,00,000.00 over the last five (5) years. Only Payment certificate or Income Tax Certificate from National Board of Revenue will be consider as annual construction turnover.
Tenderers having quoted the tender price more than 10 (Ten) percent above or below the official cost estimate, the tender will be rejected as per ITT Clause 30.3 |
| Opening Date & Time | 02/04/2020 15:00 | 08/04/2020 15:00 |
| Meeting End Date & Time | 25/03/2020 17:00 | 05/04/2020 17:00 |
| Last date & time for Tender/Proposal Security Submission | 02/04/2020 12:00 | 08/04/2020 12:00 |
| Closing Date & Time | 02/04/2020 15:00 | 08/04/2020 15:00 |
| Brief Description of Goods,Works or Service | Construction of 06 (six) storied Noyasorok Jame Mosque. |
Construction of 06 (six) storied Noyasorok Jame Mosque. |