Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Change in submission date |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 29/10/2020 | 26/11/2020 |
| Document last selling date & time | 22/04/2020 16:00 | 07/05/2020 16:00 |
| Opening Date & Time | 23/04/2020 11:00 | 10/05/2020 12:30 |
| Last date & time for Tender/Proposal Security Submission | 23/04/2020 10:30 | 10/05/2020 12:00 |
| Start Date(Lot No : 1) | 03/05/2020 | 31/05/2020 |
| Closing Date & Time | 23/04/2020 11:00 | 10/05/2020 12:30 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Changing submission date |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 12/04/2020 16:00 | 22/04/2020 16:00 |
| Eligibility of Consultant | (a) General Experience: Reputed Contactors/ Construction firms having general experience in construction works for minimum 05 (Five) year's. (b) Specific Experience : i) Must have successful completion of at least 1(one) number similar nature of Building construction works (RCC Frame structure) of Government / semi Government / Autonomous Organization in Bangladesh during last 05 (Five) years minimum amounting TK 35.00 (thirty five) Lacs, in a single contract.(ii) Last 05 (Five) years will be counted backward from the date of publication of IFT in the newspaper. (c) The Tenderers average annual construction turn over shall be greater than amounting TK. 60.00 (sixty lac) Lacs, This must be supported by total certified payment received for contracts in progress work completed under public sector during last 05 (Five) years. (d) The minimum amount of liquid assets i.e. working capital or credit facilities of the tenderer shall be amounting TK 20.00 (twenty) Lacs, Document(Original Copy Only) submitted along with the tender must be issued in between publication date and submission date of the tender in a prescribed form for this purpose (Form PW2a-3). (e) Tenders having quoted the offer in percentage is more than 10 (Ten)percent above or below the official cost estimated of the proposed works,shall be rejected. If the quoted price is same among the tenderers then evaluation process is maintained according to the ITT Clause 44.2(f) Up to date Terms & Conditions as stated in PPR 2008 and PPA 2006 will (g) The minimum Tender capacity shall be: Tk. 35.00 (thirty five lac) Lacs.h) Must have update Trade license, Vat, TIN, BIN certificate and ABC category contractory and supervisory license from Electricity Licensing Board, GoB. |
(a) General Experience: Reputed Contactors/ Construction firms having general experience in construction works for minimum 05 (Five) year's. (b) Specific Experience : i) Must have successful completion of at least 1(one) number similar nature of Building construction works (RCC Frame structure) of Government / semi Government / Autonomous Organization in Bangladesh during last 05 (Five) years minimum amounting TK 35.00 (thirty five) Lacs, in a single contract.(ii) Last 05 (Five) years will be counted backward from the date of publication of IFT in the newspaper. (c) The Tenderers average annual construction turn over shall be greater than amounting TK. 60.00 (sixty lac) Lacs, This must be supported by total certified payment received for contracts in progress work completed under public sector during last 05 (Five) years. (d) The minimum amount of liquid assets i.e. working capital or credit facilities of the tenderer shall be amounting TK 20.00 (twenty) Lacs, Document(Original Copy Only) submitted along with the tender must be issued in between publication date and submission date of the tender in a prescribed form for this purpose (Form PW2a-3).
(e) Tenders having quoted the offer in percentage is more than 10 (Ten)percent above or below the official cost estimated of the proposed works,shall be rejected. If the quoted price is same among the tenderers then evaluation process is maintained according to the ITT Clause 44.2(f) Up to date Terms & Conditions as stated in PPR 2008 and PPA 2006 will (g) The minimum Tender capacity shall be: Tk. 35.00 (thirty five lac) Lacs.h) Must have update Trade license, Vat, TIN, BIN certificate and ABC category contractory and supervisory license from Electricity Licensing Board, GoB. |
| Opening Date & Time | 13/04/2020 11:00 | 23/04/2020 11:00 |
| Meeting End Date & Time | 25/03/2020 22:00 | 15/04/2020 17:00 |
| Meeting Start Date & Time | 25/03/2020 19:00 | 15/04/2020 09:00 |
| Last date & time for Tender/Proposal Security Submission | 13/04/2020 10:30 | 23/04/2020 10:30 |
| Closing Date & Time | 13/04/2020 11:00 | 23/04/2020 11:00 |
| Brief Description of Goods,Works or Service | Vertical extension of 1st floor of DIG prisoner office 2 storied building with 4 storied foundation in Chattogram Central jail. [Re-tender] |
Vertical extension of 1st floor of DIG prisoner office 2 storied building with 4 storied foundation in Chattogram Central jail. [Re-tender] |