View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Local Government, Rural Development and Co-operatives Division : Local Government Division
Organization : Local Government Engineering Department (LGED) Procuring Entity Name : Office of the Upazila Engineer, LGED, Kahaloo, Bogra
Procuring Entity Code : Procuring Entity District : Bogura
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : APP ID-161043 Tender/Proposal Status :
App ID : 161043 Tender/Proposal ID : 458846
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government, Aid or Grant
Particular Information :
Project Code : 2242237900 Project Name : Fourth Primary Education Development Program
Tender/Proposal Package No. and Description : e-Tender/PEDP4/BRG/KAH/2019-2020/W1.0061
Construction of additional class room Niamat Pur under PEDP4 under Kahaloo Upazila District Bogura
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
21-May-2020 10:00 Tender/Proposal Document last selling /
downloading Date and Time :
21-Jun-2020 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
21-May-2020 11:00 Pre - Tender/Proposal meeting End
Date and Time :
07-Jun-2020 15:00
Tender/Proposal Closing
Date and Time :
22-Jun-2020 13:00 Tender/Proposal Opening
Date and Time :
22-Jun-2020 13:00
Last Date and Time for Tender/Proposal Security
Submission :
22-Jun-2020 12:30    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

As per Notice

Brief Description of Works :

e-Tender/PEDP4/BRG/KAH/2019-2020/W1.0061
Construction of additional class room Niamat Pur under PEDP4 under Kahaloo Upazila District Bogura

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 2000
Mode of Payment :
Tender/Proposal Security Valid Up to : 18-Oct-2020
Tender/Proposal Valid Up to : 20-Sep-2020
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
1 Construction of additional class room Niamat Pur under PEDP4 under Kahaloo Upazila, District: Bogura Kahaloo 366000 03-Aug-2020 02-May-2021
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Ahsan Habib Designation of Official Inviting Tender/Proposal : Upazila Engineer
Address of Official Inviting Tender/Proposal :
Address: Upazila Parishad, Kahaloo
City: Kahaloo
Thana: Kahaloo
District: Bogura - 5870
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 05026-56011
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Corrigendum

Field Name Old Value New Value
Document last selling date & time 14/06/2020 17:00 21/06/2020 17:00
Eligibility of Consultant

As per Notice

As per Notice

Opening Date & Time 15/06/2020 13:00 22/06/2020 13:00
PCC--A. General--

The PE is
[Name, address, and name of authorized representative]
 

The PE is
The Upazila Engineer

Local Government Engineering Department

Upazila: Kahaloo District: Bogura
 

PCC--A. General--

The Site is located at [location] and is defined in drawings No: 
[insert numbers]
 

The Site is located at Upazila: Kahaloo, District: Bogura and is defined in drawings No: 
 

PCC--A. General--

The Start Date shall be  [insert date ]

[it is the last date when the Contractor shall commence execution of  the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC  Clause 40]
 

The Start Date shall be  within 7 (seven) days from the date of signing contract.
 

PCC--A. General--

The PE is
[Name, address, and name of authorized representative]

The Development Partner is [Name of the DP]

The PE is

The Upazila Engineer

Local Government Engineering Department

Upazila: Kahaloo District: Bogura
 

The Development Partner is IDA, ADB, Unicef, JICA & EU

PCC--A. General--

The original Contract price is [insert the amount in the NOA]

The original Contract price is same as total quoted price at BOQ

PCC--A. General--

The Works consist of

[state brief summary, including relationship to other Contracts under the Project]

The Works consist of { Construction of School building & Supply of Furniture.( as per specification, BOQ and Drawings.

PCC--A. General--

The Project Manager is
[Name, address, and name of authorized representative]

 


 

The Project Manager is
 Upazila Engineer

Local Government Engineering Department

Upazila: Kahaloo District: Bogura

 


 

PCC--A. General--

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);

[state date or dates  of possession of site] 
 

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s); within 7 (seven) days from the date of signing contract


 

PCC--A. General--

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;

[insert name(s)]
 

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;

1. Project Manager (Bachelor Degree)

2.Quality Control Engineer (Diploma Engineer)

3. Works Supervisor (H.S.C.)
 

PCC--A. General--

The Sectional Completion Dates are:

[state part of the works and the corresponding dates, if applicable]
 

The Sectional Completion Dates are: N/A
 

PCC--A. General--

Nominated Subcontractor(s)  named below;

____[insert name(s)]___________________________________________
shall be entitled to execute the following specific components of the Works

[state none ,if not applicable]
 

Nominated Subcontractor(s)  named below;
shall be entitled to execute the following specific components of the Works Not Applicable


 

PCC--A. General--

The  Contractual matters between the PE and the Contractor shall be decided by

[state only  if other than the Project Manager]
 

The  Contractual matters between the PE and the Contractor shall be decided by Chief Engineer.


 

PCC--A. General--

The minimum insurance cover shall be:

(a)

The maximum deductible for insurance of the Works and of Plant and Materials is Tk [state amount]


[the Contractor shall provide this amount at the time of Contract signing].
 

(b)

The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is Tk [state amount].


[the amount could be 110% of the value of the works, plant and materials that may be lost in a worst case scenario].
 

(c)

The maximum deductible for insurance of Equipment is Tk [state amount].


[the Contractor shall provide this amount at the time of Contract signing].
 

(d)

The minimum cover for loss or damage to Equipment is Tk [state amount].


[the amount could be 110% of the replacement value of the equipment]
 

(e)

The maximum deductible for insurance of other property is Tk [state amount].


[the Contractor shall state this amount at the time of Contract signing].
 

(f)

The minimum cover for insurance of other property is Tk [state amount].


[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks – recommended value 10% of contract price].
 

(g)

The minimum cover for personal injury or death insurance:


(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.


(ii) and for third parties is as per the law and common practice in Bangladesh.
 

The minimum insurance cover shall be:

(a)

The maximum deductible for insurance of the Works and of Plant and Materials is Tk. 0.3% of contract amount.
 

(b)

The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is Tk. 110% of contract amount.

(c)

The maximum deductible for insurance of Equipment is  0.3% of Tk. 2,00,000.00

(d)

The minimum cover for loss or damage to Equipment is sum of TK. 2,00,000.00
 

(e)

The maximum deductible for insurance of other property is Tk 0.3% of contract amount.

(f)

The minimum cover for insurance of other property is Tk 10% of contract amount.

(g)

The minimum cover for personal injury or death insurance:


(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.


(ii) and for third parties is as per the law and common practice in Bangladesh.
 

PCC--A. General--

Other documents forming part of the Contract are; 

 

[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]

Other documents forming part of the Contract are;

1.annex-5 of Environment Management Framework (EMF) under PEDP-4

2. Work Program

PCC--A. General--

Materials, Equipments Plants and supplies shall not have their origin in  the following countries:

[state countries, if applicable]
 

Materials, Equipments Plants and supplies shall not have their origin in  the following countries: Israel


 

PCC--A. General--

A Contractor or a Subcontractor  that is a national of, or registered in, the following countries are not eligible:

[state countries, if applicable]
 

A Contractor or a Subcontractor  that is a national of, or registered in, the following countries are not eligible: Israel

PCC--B. Time Control--

The period between Programme updates is [state interval]

[usually bi-monthly or quarterly depending on the nature of the Works]
 

The period between Programme updates is 90 (Ninety) Days
 

PCC--B. Time Control--

The amount to be withheld for late submission of an updated Programme is [state amount].

The amount to be withheld for late submission of an updated Programme is 5% of the next payment certificate.

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.

[usually fifteen (15) days]
 

The Contractor shall submit a Programme for the Works within 14 (Fourteen) days of signing the Contract.


 

PCC--C. Quality Control--

The Defects Liability Period is [state months]

[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is twelve (12) months


 

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:


[list events or state none ]
 

The following additional events shall also be the Compensation Events: None


 

PCC--D. Cost Control--

The Contract is not subject to price adjustment.
OR
The Contract is subject to price adjustment, the weightings or coefficients for adjustment are:

[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
Example:
P= A + a (Lm/Lo)+ b (BIm/BIo)+ c (CEm/CEo)+ d (RSm/RSo)+ e (STm/STo)+ f (BRm/BRo)+g (MIm/MIo) + h (FUm/FUo)+ etc
where;
L= Labor, BI=Bitumen, CE=Cement, RS=Reinforcing Steel, ST=Stone, BR=Bricks, MI=Miscellaneous, FU= Fuel ]
Weighting or Coefficient A equals between 0.10 and 0.15 and, B (a+b+c+d+e+f+g+h+etc) equals between 0.90 and 0.85.

[insert figure] non-adjustable component (coefficient A)
[insert figure] adjustable component (coefficient B)
[The sum of A+B shall equal ONE (1). It is usual to have value of A between 0.10 and 0.15 and that of B between 0.90 and 0.85. Breakdown of B shall be provided in Appendix to the Tender.]
[delete as appropriate]

[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months]
 

The Contract is not subject to price adjustment.

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.


[state “none’ if not applicable. If applicable then the proportion of Retention Money shall be equal to the percentage-shortfall of ten (10) percent of Performance Security determined at the time of signing the Contract. Again in case of unbalanced Tender or because of front loading, provision for Retention Money shall not be applicable]
 

The proportion of payments to be retained is 5% (five) Percent for each payment.
 

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of its Contract price per day of delay]
Guide to application of GCC Sub Clause 76.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.


[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]

 

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.05 (Zero Point zero Five) of ONE (1) percent percent of its Contract price per day of delay.

T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10% (Ten)  percent of the final Contract price of the whole of the Works.




 

PCC--D. Cost Control--

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day.

The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.

[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages]
 

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. N/A

The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price. N/A


 

PCC--D. Cost Control--

The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].

[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects]
 

The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than N/A


 

PCC--D. Cost Control--

The percentage for adjustment of Provisional Sums is

____% (_________percent)
[state none, if not applicable. Usually covers the VAT, profit and overhead costs]
 

The percentage for adjustment of Provisional Sums is N/A


 

PCC--E. Completion of the Contract--

The date by which “as-built” drawings are required is [insert date]

 

The date by which operating and maintenance manuals are required is [insert date]

The date by which “as-built” drawings are required is N/A

PCC--E. Completion of the Contract--

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]

[usually a very nominal amount]
 

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is N/A


 

PCC--F. Termination and Settlement of Disputes--

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 15% (Fifteen) percent.

PCC--G. Claims, Disputes and Arbitration--

The Adjudicator jointly appointed by the parties is:
Name:
Address:
Tel No:
Fax No:
e-mail address:

 

In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Project Managers, Bangladesh. 

The Adjudicator jointly appointed by the parties is:
Name: Mr. Ali Ahmed
Address: Flat No. C-1, Metro Garden, 70/a.Indira road, West Rajabazar Dhaka-1214.
Tel No:
Fax No:
e-mail address:

 

In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Engineers Bangladesh (IEB), Bangladesh. 

PCC--G. Claims, Disputes and Arbitration--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]

The arbitration shall be conducted in the place mentioned below;
LGED HQ BhabaN,Agargaon,Dhaka.

Last date & time for Tender/Proposal Security Submission 15/06/2020 12:30 22/06/2020 12:30
Closing Date & Time 15/06/2020 13:00 22/06/2020 13:00
TDS/PDS--C. Qualification Criteria--

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five)   years.

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at 01 (One) least contract(s) of similar nature, complexity and methods/construction technology (Building Works) successfully completed within the last 05 (Five) years, each with a value of at least Tk. 79,50,000.00 (Seventy Nine Lac Fifty thousand only) .

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 05 (Five)   years.

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at 01 (One) least contract(s) of similar nature, complexity and methods/construction technology (Building Works) successfully completed within the last 05 (Five) years, each with a value of at least Tk. 79,50,000.00 (Seventy Nine Lac Fifty thousand only) .

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

The required average annual construction turnover shall be greater than Tk 1,35,00,000.00 (One Crore Thirty Five Lac Only) over the last 05 (Five) years.

 

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 36,00,000.00 ( Thirty Six Lac only)

 


 

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

The minimum capacity shall be:91,00,000.00 ( Ninety One lac taka only)
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

TDS/PDS--C. Qualification Criteria--

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
       
       
       
       
       
       

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

[ qualification of an alternative Construction Project Manager may also be requested]
[ for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package]
 

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Education Total Works Experience (years) In Similar
Works
Experience
(years)
 
1 Project Manager Bachelor Degree 03 ( Three) 02 ( Two)
2 Quality Control Engineer Diploma Engineer 2 (Two) 01 (One)
3 Works Supervisor H.S.C. 2 ( Two) 01 (One)
         
         
         

 

 

 

 


 

 

 

 

 

 

 

 

 

TDS/PDS--C. Qualification Criteria--

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required
 
     
     
     
     
     
     

 

 [for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary  for each lot in the package, subject to the nature of the control required over each package]

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required
 
1 Mixture Machine 1
2 Vibrator Machine 1
     
     
     
     

 

TDS/PDS--C. Qualification Criteria--

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

[it is suggested that the PE adheres to the above proportion of minimum qualifying requirements to meet the specific procurement needs. Percent share of business of the JVCA partners shall not be taken into account in determining the qualification of a JVCA]
 

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

 

TDS Clauses References Requirements by Summation Requirements for Lead Partner of JVCA Requirements for other Partner (s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for Leading Partner
ITT-15.1(b) 100% At least one Contract Minimum requirment not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable
TDS/PDS--C. Qualification Criteria--

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable

 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount]
[the value of the non-judicial stamp shall be Tk.300.00]
 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk. 300

 

TDS/PDS--C. Qualification Criteria--

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:


[state the components of the proposed works ; if not applicable state ‘none’]
 

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works: None



 

TDS/PDS--D. Tender Preparation--

The Tenderer shall submit with its Tender the following additional documents:


[in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required then specify “none”]

 

The Tenderer shall submit with its Tender the following additional documents:

Annex-5 of Environment Management Framework (EMF) under PEDP4

 

TDS/PDS--D. Tender Preparation--

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
OR
The prices quoted by the Tenderer shall be adjustable as follows:

Iif prices shall be adjustable, the methodology for adjustment should be specified]
 

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.

TDS/PDS--E. Tender e-Submission--

The deadline for lodgement of e-Tenders is 12:30 PM, 15-06-2020
 

The deadline for lodgement of e-Tenders is 12:30 PM, 22-06-2020
 

TDS/PDS--G. Contract Award--

The amount of Performance Security shall be [state percentage] percent of the Contract Price.

[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ]
 

The amount of Performance Security shall be 5% (FIVE) percent of the Contract Price.

Brief Description of Goods,Works or Service

e-Tender/PEDP4/BRG/KAH/2019-2020/W1.0061
Construction of additional class room Niamat Pur under PEDP4 under Kahaloo Upazila District Bogura

e-Tender/PEDP4/BRG/KAH/2019-2020/W1.0061
Construction of additional class room Niamat Pur under PEDP4 under Kahaloo Upazila District Bogura

 
Save As PDF