The Tenderer should have the following criteria:
01) A satisfactory/substantially completion of similar works of at least Taka 30,00,000.00 under single contract over a period of last five years years shall be required. Substantially completed contracts may be taken into account, if others criteria are fully met.
02) The required average annual construction turnover shall be greater than Taka 24,00,000.00 over a period of last 05(five) years.
03) The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Taka 21,00,000.00 [Only the amount supported by the Bank statement, savings instrument(s) and lines of credit, if any, will be ta
Periodic Maintenance of Nabiganj-inathgonj Road(Ch.9200-11500m). (Nabiganj)(Earth Work, WBM,Dense carpeting)