View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Railways Division :
Organization : Bangladesh Railway Procuring Entity Name : Office of the Chief Engineer (East), Chittagong
Procuring Entity Code : Procuring Entity District : Chattogram
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : xenpne/east/e-tender/2020-21/03 Tender/Proposal Status :
App ID : 167257 Tender/Proposal ID : 482108
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Revenue
Source of Funds : Government
Particular Information :
Project Code : Not applicable Project Name : Not applicable
Tender/Proposal Package No. and Description : DA-2-1/2020-21/KA-2
At SSAE/Works/BCI section Raising of platform no.1 from existing level to equal 2-3 height from rail top by RCC works at NRC station as per drawing.
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
09-Aug-2020 17:00 Tender/Proposal Document last selling /
downloading Date and Time :
31-Aug-2020 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
10-Aug-2020 10:00 Pre - Tender/Proposal meeting End
Date and Time :
20-Aug-2020 12:00
Tender/Proposal Closing
Date and Time :
01-Sep-2020 12:00 Tender/Proposal Opening
Date and Time :
01-Sep-2020 12:00
Last Date and Time for Tender/Proposal Security
Submission :
01-Sep-2020 11:00    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

As a stated in the Tender Document.

Brief Description of Works :

At SSAE/Works/BCI section : Raising of platform no.1 from existing level to equal 2-3 height from rail top by RCC works at NRC station as per drawing.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 2000
Mode of Payment :
Tender/Proposal Security Valid Up to : 27-Jan-2021
Tender/Proposal Valid Up to : 30-Dec-2020
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
00 At SSAE/Works/BCI section: Raising of platform no.1 from existing level to equal 2'-3" height from rail top by RCC works at NRC station as per drawing. Narshingdi Station 380000 27-Sep-2020 25-Mar-2021
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Shuboktagin Designation of Official Inviting Tender/Proposal : CE,CME,CSTE,COPS,CCM,JDG
Address of Official Inviting Tender/Proposal :
Address: CRB, Chittagong
City: Chittagong
Thana: Kotoali
District: Chattogram - 4000
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 031-2863162
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  3 
Amendment / Corrigendum Text :

Corrigendum for tender notice

Field Name Old Value New Value
Document last selling date & time 26/08/2020 12:00 31/08/2020 17:00
Opening Date & Time 27/08/2020 12:00 01/09/2020 12:00
Last date & time for Tender/Proposal Security Submission 27/08/2020 11:00 01/09/2020 11:00
Closing Date & Time 27/08/2020 12:00 01/09/2020 12:00
 Amendment / Corrigendum No. :  2 
Amendment / Corrigendum Text :

Corrigundum for tender document

Field Name Old Value New Value
PCC--A. General--

Possession of the Site to the Contractor shall be given on the following date; within 07 (Seven) days after signing of contract agreement.

Possession of the Site to the Contractor shall be given on the following date; within 07 (Seven) days after signing of contract agreement or actual date of handover of site to contractor by concern DEN/AEN which happend later on.

PCC--B. Time Control--

The Start Date shall be within 7 (Seven) days after signing of Contract Agreement.

The Start Date shall be within 7 (Seven) days after signing of Contract Agreement or actual commence date of works declared  by concern DEN/AEN which happend later on.

PCC--B. Time Control--

The Intended Completion Date for the whole of the Works shall be 180 (One hundred Eighty ) days after signing of Contract Agreement.

The Intended Completion Date for the whole of the Works shall be 180 (One hundred Eighty ) days after signing of Contract Agreement or actual commencement date of works declared by concern DEN/AEN.

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within 10 (Ten) days from signing of Contract Agreement.

The Contractor shall submit a Programme for the Works within 10 (Ten) days from signing of Contract Agreement. Otherwise concern DEN may with held Tk. 1,00,000.00 (One lakh) from 1st CC bill.

PCC--C. Quality Control--

The Defects Liability Period is 12 (twelve) months.


 

The Defects Liability Period is 12 (twelve) months from date of completion of works.


 

PCC--D. Cost Control--

The proportion of payments to be retained is: 10 (Ten) percent of the contract price.

a) 5% of the total contract price Pay order/Bank gurantee will be submitted by the successfull bidder as performance security.

b) 5% will be retained as retention money from each progressive payment.

(After successfull completion of the whole works 5% performance security will be refunded to the contractor)

The proportion of payments to be retained is: 10 (Ten) percent of the contract price.

a) 5% of the total contract price in the form of Pay order/Bank guarantee have to be submitted by the successfull bidder as performance security.

b) 5% will be retained as retention money from each progressive payment.

(After successfull completion of the whole works 5% performance security will be refunded to the contractor)

PCC--D. Cost Control--

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works.

The maximum amount of Liquidated Damages in case of fail to complete the works wihtin stipulated time/delay in completion of works or any part thereof is 10 (Ten) percent of the final Contract price of the whole of the Works.

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages is 0.10 of o1 (one) percent of final Contract price for per day of delay or part there of.

The amount of Liquidated Damages or in other words Delay Damages is 0.10 of 1% (One Percent) of final Contract price of the whole of the works per day of delay or any part thereof.

PCC--F. Termination--

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 (Ten) percent of the official estimated cost of the uncompleted works

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the incompleted Works, is 20 (Twenty percent) of the official estimated cost of the incompleted works

TDS/PDS--B. Tender Document--

Allowed to post clarification till 24-Aug-2020 at 12:00 PM

Allowed to post clarification till 24-Aug-2020 at 12:00 PM

TDS/PDS--C. Qualification Criteria--

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 40.00 (Fourty) lakh shall be submitted as per standard document prescribe form Letter of Commitment for Bank’s Undertaking for Line of Credit (Form PW2a-3).

[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 40.00 (Fourty) lakh shall be submitted as per standard document prescribe form Letter of Commitment for Bank’s Undertaking for Line of Credit (Form PW2a-3).

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be: Not applicable.

The minimum capacity shall be: Not applicable.

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk. 92.00 (Ninety Two Lakh ) over the best 05 (five) years in the last 10 (Ten) years.

The required average annual construction turnover shall be greater than Tk. 92.00 (Ninety Two Lakh ) over the best 05 (five) years.

TDS/PDS--C. Qualification Criteria--

 

A satisfactory completion of similar works of at least Tk. 80.00 (Eighty Lakh ) under 01 (one) number of contract or part of contract over the last 10 (Ten) years shall be required.

 

[Here Similar works means construction/re-construction in any civil works successfully completed in Govt./Semi Govt./Autonomous Authority in a single contract or part of contract]

 

A satisfactory completion of similar works of at least Tk. 80.00 (Eighty Lakh ) under 01 (one) number of contract or part of contract over the last 05 (five) years shall be required.

 

[Here Similar works means construction/re-construction in any civil works successfully completed in Govt./Semi Govt./Autonomous Authority in a single contract or part of contract]

 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Corrigendum for Tender Document

Field Name Old Value New Value
Eligibility of Consultant

As a stated in the Tender Document.

As a stated in the Tender Document.

Brief Description of Goods,Works or Service

At SSAE/Works/BCI section : Raising of platform no.1 from existing level to equal 2-3 height from rail top by RCC works at NRC station as per drawing.

At SSAE/Works/BCI section : Raising of platform no.1 from existing level to equal 2-3 height from rail top by RCC works at NRC station as per drawing.

Amendment / Corrigendum/ Addendum No. : 1
S. No. File Name File Description File Size
(in KB)
1 Section-7 NRC Rasing platform.doc Section-7 General Specificatiobn 135944
2 Section 8 BCI Rasing platform.docx Section-8 Particular Specification 37988
3 Section 9.docx Section-9 Drawing 15918
 
Save As PDF