View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | TDS & PCC Correction. |
| Field Name | Old Value | New Value | ||||
|---|---|---|---|---|---|---|
| Document last selling date & time | 02/05/2016 12:30 | 02/05/2016 16:00 | ||||
| PCC--A. General-- |
The Procuring Entity is |
The Procuring Entity is The Executive Engineer, LGED, Chapai Nawabagnj. |
||||
| PCC--A. General-- |
The Works consist of |
The Works consist of Patch Repair, Carpeting & Seal Coat work |
||||
| PCC--A. General-- |
The Project Manager is |
The Project Manager is Upazila Engineer Gomostapur Upazila |
||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at Gomostapur Upazila and is defined in drawings No: |
||||
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; none. |
||||
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date;
[state date of possession of site] |
Possession of the Site to the Contractor shall be given on the following date; [Within 10 days of signing contract] |
||||
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
The Start Date shall be Within 10 days of signing contract |
||||
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be Start Date + 180 Days. |
||||
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programme for the Works within 10 days of signing the Contract. |
||||
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is Twelve (12) months |
||||
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
If The following additional events shall also be the Compensation Events: the contract is terminated following the fundamental breach of contract by the contractor. To quantify such Compensation the steps mentioned below shall apply: (i) A Compensation Assessment Commitee comprising of minimum 03 (Three) members shall be formed by the Procuring Enti/Project Manager to assess the Compensation to complete the remaining works as per latest LGED rate schedule. this Assessed Compensation would be the Estimated Cost of Uncompleted Contract Quantity as per latest LGED rate schedule less the Quoted amount of the same by the Terminated Contractor representing in percent (%) w.r.t. Uncompleted Contract Amount of the Terminated Contract but in no case it shall be less than minimum 10(Ten)% of the Uncompleted Contract Amount. (ii) The Assessed Compensation as recommended by the Compensation Assessmet Committee shall be recoverable as instructed in GCC clause 47.
|
||||
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is 5(Five) percent. |
||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 0.05 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
||||
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
||||
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract vale of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted works, is compensation assessed as mentioned in PCC 28(f).
1. Compensation Amount= Cost of Remaining work as per latest LGED rate Schedule – Cost of Remaining Work as per quoted rate.
|
||||
| PCC--G. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; LGED, HQ, Dhaka. |
||||
| Last date & time for Tender/Proposal Security Submission | 02/05/2016 12:31 | 02/05/2016 16:00 | ||||
| Closing Date & Time | 02/05/2016 12:35 | 03/05/2016 12:30 | ||||
| TDS/PDS--A. General-- |
|
|
||||
| TDS/PDS--B. Tender Document-- | Allowed to post clarification till [Date and Time] |
Allowed to post clarification till : Not Applicable. |
||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)] |
The required average annual construction turnover shall be greater than Tk.13.00 (Thirteen) Lakh in the best 5(five) years over the last 10 (ten) years. years counting backward from the date of publication of IFT in the newspaper. |
||||
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.] |
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit line of the Tenderer shall be Tk.7.00(Seven) Lakh Only. |
||||
| TDS/PDS--C. Qualification Criteria-- | A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required. [the minimum value of the similar works under a single or multiple number of contract(s) is recommended to be between 50 and 75 percent of the estimated cost, rounded off to nearest Taka thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package] |
A satisfactory completion of similar works of at least Tk.13.00(Thirteen) Lakh under max. 4 (four) numbers of contracts over a period of last 10 (ten) years shall be required. years counting backward from the date of publication of IFT in the newspaper] |
||||
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents: |
Tenderer shall submit with its Tender, the following additional documents: None. |
||||
| TDS/PDS--D. Tender Preparation-- | The Tender Validity period shall be [state number] days.
[normally 60 to 90 days deemed reasonable] |
The Tender Validity period shall be 120 days. |
||||
| TDS/PDS--D. Tender Preparation-- |
The amount of the Tender Security shall be [ state amount ] |
The amount of the Tender Security shall be Tk.60000.00 (Sixty Thousand) Only. |
||||
| TDS/PDS--E. e-Tender Submission-- |
The deadline for lodgment of e-Tenders is [state time, and identify AM or PM e.g 10.30 a.m] |
The deadline for lodgment of e-Tenders is Date & Time: 03 May 2016, 12.30. |