View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Due to unavoidable circumstances some changes has been made in this e tender documents |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
The Start Date shall be 30-June-2016 |
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be 31-Oct-2016 |
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be 31-Oct-2016 |
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programme for the Works within 10 days of signing the Contract. |
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is 12 months |
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
The following additional events shall also be the Compensation Events: |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is 10 percent. At the time of final bill application, tenderer must submit as built drawing and pressure test result |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 0.05 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 percent.
|
| TDS/PDS--C. Qualification Criteria-- |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 35 Lac (Please note that in case of Line of Credit Certificate as a Liquid Asset certificate, the Certificate must be in prescribed formate of PW2a-3, attached in Particular Specifications section of this e Tender documents.) |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 35 Lac Please note the following : 1) In case of Line of Credit Certificate as a Liquid Asset certificate, the Certificate must be in prescribed formate of PW2a-3, attached in Particular Specifications section of this e Tender documents. 2) The certificate must be substantiated by any scheduled Bank of Bangladesh in the format as specified (Form PW2a-3) ,without alteration, issued not earlier than twenty eight (28) days prior to the day of the original deadline for submission of Tenders |