View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Energy, Power and Minearal Resources Division : Power Division
Organization : Power Grid Company of Bangladesh Ltd. (PGCB) Procuring Entity Name : Grid Maintenance Division, Cumilla
Procuring Entity Code : 014 Procuring Entity District : Cumilla
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : 27.21.1933.691.44.052.20.153 dated: 23.02.21 Tender/Proposal Status :
App ID : 167589 Tender/Proposal ID : 551448
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Own Fund
Source of Funds : Own Fund
Particular Information :
Project Code : Not applicable Project Name : Not applicable
Tender/Proposal Package No. and Description : eTgmd/com/Feni/20-21/05
Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD PGCB Cumilla.
Category : Electricity, gas, nuclear energy and fuels, steam, hot water and other sources of energy;Electricity;Manufactured gas;Coal gas or similar gases;Mains gas;Steam, hot water and associated products;Hot water;Steam;District heating;Long-distance heating;Solar energy;Solar panels;Solar installation;Nuclear fuels;Uranium;Plutonium;Radioactive materials;Radio-isotopes
Scheduled Tender/Proposal Publication
Date and Time :
28-Feb-2021 15:00 Tender/Proposal Document last selling /
downloading Date and Time :
15-Mar-2021 15:00
Pre - Tender/Proposal meeting Start
Date and Time :
01-Mar-2021 10:00 Pre - Tender/Proposal meeting End
Date and Time :
01-Mar-2021 11:00
Tender/Proposal Closing
Date and Time :
16-Mar-2021 12:00 Tender/Proposal Opening
Date and Time :
16-Mar-2021 12:00
Last Date and Time for Tender/Proposal Security
Submission :
16-Mar-2021 11:30    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

Any genuine contractor having valid up to date ABC Electrical license, trade license and as per TDS and PCC. Tenderers are requested to go through carefully with attched documents before submission of tender.

Brief Description of Works :

Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD PGCB Cumilla.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 1000
Mode of Payment :
Tender/Proposal Security Valid Up to : 12-Sep-2021
Tender/Proposal Valid Up to : 14-Jun-2021
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
01 Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD, PGCB, Cumilla. Feni 8400 01-Apr-2021 27-May-2021
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Jashim Uddin Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: Biddut bhaban, Jangalia, Comilla
City: Comilla
Thana: Jangalia
District: Cumilla - 3500
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 081-64752
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Update TDS, PCC

Field Name Old Value New Value
PCC--A. General--

The Procuring Entity is
[Name, address]
 

The Procuring Entity is
Md Jashim Uddin
Executive Engineer
GMD, PGCB, Comilla.
 

PCC--A. General--

The Project Manager is
[Name, address]
 

The Project Manager is
Md. Jalal Uddin
Assistant Engineer (A.C)
Feni Grid Substation
GMD, PGCB, Cumilla
 

PCC--A. General--

The Site is located at [location] and is defined in drawings No:
[insert numbers]
 

The Site is located at [Feni] and is defined in drawings No:N/A

PCC--A. General--

The Works consist of
[state brief summary]
 

The Works consist of Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD PGCB Cumilla.

PCC--A. General--

Other documents forming part of the Contract are;

[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]
 

Other documents forming part of the Contract are;N/A

PCC--A. General--

Possession of the Site to the Contractor shall be given on the following date;

[state date of possession of site]
 

Possession of the Site to the Contractor shall be given on the following date: Within 4 or 5 days of contract signing.

PCC--B. Time Control--

The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract]
 

The Start Date shall be 01-Apr-2021

PCC--B. Time Control--

The Intended Completion Date for the whole of the Works shall be [insert date]
[to be calculated from the start Date]
 

The Intended Completion Date for the whole of the Works shall be 27-May-2021

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually ten (10) days or may be less]
 

The Contractor shall submit a Programme for the Works within [07] days of signing the Contract.

PCC--C. Quality Control--

The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is [12 months]

 

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.

The proportion of payments to be retained is [10%] percent.

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay]
Guide to application of GCC Sub Clause 28.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x P x n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price.
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay of the final Contract price of the uncompleted Works or any part there of.
n = No of days of delay for completion of works under the Contract]
 

The amount of Liquidated Damages or in other words Delay Damages is [0.05] percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay.

PCC--D. Cost Control--

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]
 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [10] percent of the final Contract price of the whole of the Works.

PCC--F. Termination--

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is [20] percent.

PCC--H. Disputes and Settlement--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]
 

The arbitration shall be conducted in the place mentioned below;
[DC Office,Comilla]
 

TDS/PDS--A. General--

 

The PE is [state name of PE]

 

 

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:
Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

 

The Procuring Entity is
Md Jashim Uddin
Executive Engineer
GMD, PGCB, Comilla.
 

 

 

The Name of the Tender is: Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD PGCB Cumilla.
Brief Description of the Works: Repair and maintenance of Boundary wall including Painting at Feni 132 Kv Grid Substation under GMD PGCB Cumilla.

Tender Ref: 27.21.1933.691.44.052.20.153 dated: 23.02.21
Lot No(s): 01


 

TDS/PDS--B. Tender Document--

Allowed to post clarification till [Date and Time]

Allowed to post clarification till N/A

TDS/PDS--C. Qualification Criteria--

The minimum amount of liquid assets or working capital or credit facilities of the  Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:
Contract Value:   Tk 24 lakh
Contract period:   12 months
Assuming work time:  1 month
Invoice period:    0.5 month
Certification Time:   0.5 month
Contingency Time:   1 month

Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The minimum amount of liquid assets or working capital or credit facilities of the  Tenderer shall be Tk 200000/=

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
 

The minimum capacity shall be:200000/=

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction  turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be  best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)]
Example:
Estimated Contract Value:  Tk 24 lakh
Contract period:   12 months
Estimated Annual Cash Flow:  Tk 24 lakh
Required average annual construction turn over: Tk 12 lakh, using a multiplier of 0.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The required average annual construction turnover shall be greater than Tk 2,00,000/= over the last 03 years.

TDS/PDS--C. Qualification Criteria--

A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required.

[the minimum value of the similar works under a single or multiple number of  contract(s) is recommended to be between 50  and 75 percent of the estimated cost, rounded off to nearest Taka  thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]

[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package]
 

A satisfactory completion of similar works of at least Tk [2,00,000/=] under [01] of contract(s) over a period of [03] years shall be required.

TDS/PDS--D. Tender Preparation--

Tenderer shall submit with its Tender, the following additional documents:

Tenderer shall submit with its Tender, the following additional documents:

1. Valid ABC Electrical License
2. Updated Trade license
3. Updated VAT / IT documents
4. Similar work experiences
5. Liquid asset
6. National ID
7. Authorization letter
 

TDS/PDS--D. Tender Preparation--

The Tender Validity period shall be [state number] days.

[normally 60 to 90 days deemed reasonable]
 

The Tender Validity period shall be 90 days.


 

TDS/PDS--D. Tender Preparation--

The amount of the Tender Security shall be [ state amount ]
[note: Not exceeding three percent (3%) of the official estimated cost but as a fixed amount] 

 

The amount of the Tender Security shall be 8400/= in favor of Power Grid Company of Bangladesh Ltd. in the form of Pay order / bank draft

TDS/PDS--E. e-Tender Submission--

The deadline for lodgment of e-Tenders is [state time, and identify AM or PM e.g 10.30 a.m]
[state date, e.g 15 June,2011  ].
 

The deadline for lodgment of e-Tenders is 16-Mar-2021 12:00

 