View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Railways Division :
Organization : Bangladesh Railway Procuring Entity Name : Office of the Chief Engineer (East), Chittagong
Procuring Entity Code : Procuring Entity District : Chattogram
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : xenpne/east/e-tender/20-21/255 Tender/Proposal Status :
App ID : 167257 Tender/Proposal ID : 592319
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Revenue
Source of Funds : Government
Particular Information :
Project Code : Not applicable Project Name : Not applicable
Tender/Proposal Package No. and Description : DA-3.121.311/10/20-21/KA-2
At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
30-Jun-2021 20:00 Tender/Proposal Document last selling /
downloading Date and Time :
04-Aug-2021 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
01-Jul-2021 11:07 Pre - Tender/Proposal meeting End
Date and Time :
28-Jul-2021 16:07
Tender/Proposal Closing
Date and Time :
05-Aug-2021 12:00 Tender/Proposal Opening
Date and Time :
05-Aug-2021 12:00
Last Date and Time for Tender/Proposal Security
Submission :
05-Aug-2021 11:00    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

As a stated in tender document.

Brief Description of Works :

At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 3000
Mode of Payment :
Tender/Proposal Security Valid Up to : 31-Dec-2021
Tender/Proposal Valid Up to : 03-Dec-2021
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
00 At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing. At Komolapur Station 562000 03-Oct-2021 28-Feb-2022
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Shuboktagin Designation of Official Inviting Tender/Proposal : CE,CME,CSTE,COPS,CCM,JDG
Address of Official Inviting Tender/Proposal :
Address: CRB, Chittagong
City: Chittagong
Thana: Kotoali
District: Chattogram - 4000
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 031-2863162
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  2 
Amendment / Corrigendum Text :

Corrigendum for tender notice

Field Name Old Value New Value
Document last selling date & time 28/07/2021 17:00 04/08/2021 17:00
Opening Date & Time 29/07/2021 12:00 05/08/2021 12:00
Last date & time for Tender/Proposal Security Submission 30/06/2021 11:00 05/08/2021 11:00
Closing Date & Time 29/07/2021 12:00 05/08/2021 12:00
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Corrigendum for tender document.

Field Name Old Value New Value
Eligibility of Consultant

As a stated in tender document.

As a stated in tender document.

PCC--A. General--

The PE is
[Name, address, and name of authorized representative]
 

The PE is Chief Engineer (East), Bangladesh Railway, CRB, Chattogram.

PCC--A. General--

The original Contract price is [insert the amount in the NOA]

The original Contract price is : Will be incorporated through issuing of NoA.

PCC--A. General--

The Site is located at [location] and is defined in drawings No: 
[insert numbers]
 

The Site is located at Kamalapur Railway station Dhaka and is defined in drawings No:  As per approved drawing.

PCC--A. General--

The Start Date shall be  [insert date ]

[it is the last date when the Contractor shall commence execution of  the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC  Clause 40]
 

The start date shall be 7 (Seven) days after getting possession of the site.

PCC--A. General--

The PE is
[Name, address, and name of authorized representative]

 

The Development Partner is [Name of the DP]

The PE is Chief Engineer (East), Bangladesh Railway, CRB, Chattogram.

The Development Partner is: None

PCC--A. General--

The Contractor is
[Name, address, and name of authorized representative]
 

The Contractor is :Will be nominated through issuing of NoA.

PCC--A. General--

The Project Manager is
[Name, address, and name of authorized representative]
 

The Project Manager is: Divisional Engineer-3, Bangladesh Railway, Komolapur, Dhaka.

PCC--A. General--

The Works consist of

[state brief summary, including relationship to other Contracts under the Project]

The Works consist of At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

PCC--A. General--

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);

[state date or dates  of possession of site] 
 

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s): 07 days from the date of signing of the contract.

PCC--A. General--

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;

[insert name(s)]
 

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;

 

i) Project Engineer- Minimum Diploma in Civil Engineer, 10 years experience.

PCC--A. General--

The Sectional Completion Dates are:

[state part of the works and the corresponding dates, if applicable]
 

The Intended Completion Date for the whole of the Works shall be 04(Four) months from the Signing of the Contract or actual commencement date of works declared by concern DEN.

PCC--A. General--

Nominated Subcontractor(s)  named below;

____[insert name(s)]___________________________________________
shall be entitled to execute the following specific components of the Works

[state none ,if not applicable]
 

Nominated Subcontractor(s) named below; Not Applicable

PCC--A. General--

The  Contractual matters between the PE and the Contractor shall be decided by

[state only  if other than the Project Manager]
 

The Contractual matters between the Procuring Entity and the Contractor shall be decided by Project Manager.

PCC--A. General--

The PE’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:


The Contractor’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:

The PE’s address for the purpose of communications under this contract is :
Contact person: Chief Engineer (East) & Project Director
Address: Chief Engineer (East), Bangladesh Railway, CRB, Chittagong.
Tel: 031-2863162 (office)
e-mail address: cee@railway.gov.bd

The Contractor’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:

PCC--A. General--

Other documents forming part of the Contract are; 

 

[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]

Other documents forming part of the Contract are: Correspondences and/or clarification made to the tenderer from time to time prior to signing of the Contract agreement.

PCC--A. General--

A Contractor or a Subcontractor  that is a national of, or registered in, the following countries are not eligible:

[state countries, if applicable]
 

A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible: Israel

PCC--A. General--

Materials, Equipments Plants and supplies shall not have their origin in  the following countries:

[state countries, if applicable]
 

Materials, Equipments Plants and supplies shall not have their origin in the following countries: Israel

PCC--B. Time Control--

Commencement Date of Works shall be as follows;

[insert different commencement dates for different parts of the Works, if deemed appropriate]
 

Commencement Date of Works shall be as follows: 07(Seven) days after given the possession of the site.

PCC--B. Time Control--

The period between Programme updates is [state interval]

[usually bi-monthly or quarterly depending on the nature of the Works]
 

The period between Programme updates is 30 (Thirty) days.

PCC--B. Time Control--

The amount to be withheld for late submission of an updated Programme is [state amount].

The amount to be withheld for late submission of an updated Programme is Tk. 1.00 (One) Lakh.

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.

[usually fifteen (15) days]
 

The Contractor shall submit a Programme for the Works within 15 (Fifteen) days of signing the Contract.

PCC--C. Quality Control--

The Defects Liability Period is [state months]

[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is twelve (12)months.

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:


[list events or state none ]
 

The following additional events shall also be the Compensation Events: None

PCC--D. Cost Control--

The Contract is not subject to price adjustment.
OR
The Contract is subject to price adjustment, the weightings or coefficients for adjustment are:

[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
Example:
P= A + a (Lm/Lo)+ b (BIm/BIo)+ c (CEm/CEo)+ d (RSm/RSo)+ e (STm/STo)+ f (BRm/BRo)+g (MIm/MIo) + h (FUm/FUo)+ etc
where;
L= Labor, BI=Bitumen, CE=Cement, RS=Reinforcing Steel, ST=Stone, BR=Bricks, MI=Miscellaneous, FU= Fuel ]
Weighting or Coefficient A equals between 0.10 and 0.15 and, B (a+b+c+d+e+f+g+h+etc) equals between 0.90 and 0.85.

[insert figure] non-adjustable component (coefficient A)
[insert figure] adjustable component (coefficient B)
[The sum of A+B shall equal ONE (1). It is usual to have value of A between 0.10 and 0.15 and that of B between 0.90 and 0.85. Breakdown of B shall be provided in Appendix to the Tender.]
[delete as appropriate]

[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months]
 

The Contract is not subject to price adjustment.

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.


[state “none’ if not applicable. If applicable then the proportion of Retention Money shall be equal to the percentage-shortfall of ten (10) percent of Performance Security determined at the time of signing the Contract. Again in case of unbalanced Tender or because of front loading, provision for Retention Money shall not be applicable]
 

The proportion of payments to be retained is: 10 (Ten) percent. [ 5% as perfomance security and 5% as retention money]

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of its Contract price per day of delay]
Guide to application of GCC Sub Clause 76.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.


[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]

 

The amount of Liquidated Damages is 0.05 percent of the uncompleted works or any part thereof completed after expiry of the Intended Completion Date or extended Intended Completion Date, as applicable, per day of delay.

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is TEN (10) percent of the final Contract price of the whole of the Works.

PCC--D. Cost Control--

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day.

The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.

[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages]
 

The Bonus for the whole of the Works is Not Applicable

PCC--D. Cost Control--

The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].

[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects]
 

The Advance Payment shall be : No Advanced Payment shall be made.

PCC--D. Cost Control--

The percentage for adjustment of Provisional Sums is

____% (_________percent)
[state none, if not applicable. Usually covers the VAT, profit and overhead costs]
 

The percentage for adjustment of Provisional Sums is: Not Applicable

PCC--E. Completion of the Contract--

The date by which “as-built” drawings are required is [insert date]

 

The date by which operating and maintenance manuals are required is [insert date]

The date by which “as-built” drawings are required is within 30 days of completion of the whole of the works.

PCC--E. Completion of the Contract--

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]

[usually a very nominal amount]
 

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk 5 (Five) Lakh.

PCC--F. Termination and Settlement of Disputes--

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is ten (10) percent.

PCC--G. Claims, Disputes and Arbitration--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]

The arbitration shall be conducted in the place mentioned below;
[16, Abdul Gani Road, RailBhaban, Dhaka]

TDS/PDS--A. General--

The PE is [state name of PE]

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:

Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

The PE is Chief Engineer (East) Bangladesh Railway, CRB, Chattogram.

 

The Name of the Tender is: At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.


Brief Description of the Works: At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

 

 

Tender Ref: xenpne/east/e-tender/20-21/255

 

Lot No(s):00

TDS/PDS--A. General--

The PE is [state name of PE]

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:

Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

The PE is Chief Engineer (East) Bangladesh Railway, CRB, Chattogram.

 

The Name of the Tender is: At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.


Brief Description of the Works: At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

 

 

Tender Ref: xenpne/east/e-tender/20-21/255

 

Lot No(s):00

TDS/PDS--A. General--

The name of the Development Partner is

[state name of Development Partner]
 

The name of the Development Partner is: None

TDS/PDS--A. General--

The source of public funds is

[state source, GoB or other source of funds].
 

The source of public funds is: GoB 

TDS/PDS--A. General--

Tenderers from the following countries are not eligible

[ state countries, if any ]
 

Tenderers from the following countries are not eligible:Israel.

TDS/PDS--A. General--

Materials, Equipments and associated services from the following countries are not eligible:

[state countries, if any]
 

Materials, Equipments and associated services from the following countries are not eligible:Israel.

TDS/PDS--B. e-Tender Document (e-TD)--

Allowed to post clarification till [Date and Time]

Allowed to post clarification till 29-July-2021 12:00 PM

TDS/PDS--B. e-Tender Document (e-TD)--

A Pre-Tender meeting shall not be held
or
A Pre- Tender meeting shall be held through e-GP System

[delete whichever is not applicable]
 

A Pre- Tender meeting shall be held through e-GP System.

TDS/PDS--B. e-Tender Document (e-TD)--

Pre- Tender meeting [Date & Time]

Pre- Tender meeting 01 July-2021 11:00 am to 28-July-2021 17:00 pm

TDS/PDS--C. Qualification Criteria--

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be [state number] years.

[a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper]

 

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least [state number] contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last [state number] years, each with a value of at least Tk. [state amount].

[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
 

[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package]
[the minimum value of the similar works is recommended to be between 50 and 75 percent of the estimated cost of the proposed work]

 

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 10 (Ten) years. Years counting backward from the date of publication of IFT in the newspaper.

 

 

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 Number of contract of similar nature, complexity and methods/construction technology successfully completed/substantially completed whose billed amount or executed quantity within the last 05 (Five) years with a value of at least Tk. 118.00(One Hundred Eighteen) Lakh .

 

[ Similar works means construction /Re-construction/ repairs of any civil works successfully completed/Substantially completed under any govt./semi govt./autonomous authority shall be allowed in a single contract]

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

a) The required average annual construction turnover shall be greater than Tk. 708.00 (Seven Hundred Eight) Lakh over the best 03 (Three) years of the last 05 (Five) years.

 

b) The Liquid asset ( working capital or credit line(s) from any Scheduled Bank) will be minimum TK. 110.00 (One Hundred Ten) Lakh

 

c) Satisfactory resolution of all claims, arbitrations or other litigation cases and shall not have serious negative impact on the financial capacity of Tenderer.

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

The minimum tender capacity shall be: TK. 165.00 (One Hundred Sixty Five) Lakh.

[Attach the minimum tender capacity calculation sheet and year wise turnover]


The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

TDS/PDS--C. Qualification Criteria--

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
       
       
       
       
       
       

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

[ qualification of an alternative Construction Project Manager may also be requested]
[ for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package]
 

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)

 
1 Project Manager – minimum Diploma in Civil Engineer- 01 (One) Nos. 15 years (Minimum) 05 years (Minimum)
       
       
       
       
       

 

 

 

 


 

 

 

 

TDS/PDS--C. Qualification Criteria--

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required
 
     
     
     
     
     
     

 

 [for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary  for each lot in the package, subject to the nature of the control required over each package]

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required

 
1 Concrete Mixing machine 02 Nos
2 Vibrator 02 Nos
3 Water Pump 01 Nos
4 Diesel Generator 01 Nos
5 Excavator 01 Nos
     
TDS/PDS--C. Qualification Criteria--

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

[it is suggested that the PE adheres to the above proportion of minimum qualifying requirements to meet the specific procurement needs. Percent share of business of the JVCA partners shall not be taken into account in determining the qualification of a JVCA]
 

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Requirements by summation Same as stated in TDS  Same as for
Leading Partner
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a)  100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable



[it is suggested that the PE adheres to the above proportion of minimum qualifying requirements to meet the specific procurement needs. Percent share of business of the JVCA partners shall not be taken into account in determining the qualification of a JVCA]
 

TDS/PDS--C. Qualification Criteria--

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable

 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount]
[the value of the non-judicial stamp shall be Tk.300.00]
 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk :300

TDS/PDS--C. Qualification Criteria--

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:


[state the components of the proposed works ; if not applicable state ‘none’]
 

The Nominated Subcontractor(s) named [Nill] shall execute the following specific components of the proposed Works: None

TDS/PDS--D. Tender Preparation--

The Tenderer shall submit with its Tender the following additional documents:


[in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required then specify “none”]

 

The Tenderer shall submit with its Tender the following additional documents:


(a) Tenderers shall furnish specific experience certificates from govt./ semi govt./ autonomous authority.

(b) CV with recent photographs, educational and experience certificates of the manpower proposed for the work as mentioned.

(c) Ownership certificate/ authorization letter from owner for using major construction equipments.

(d) Updated/up to date VAT Registration Certificate ( 13 Digit BIN).

(e) Updated/up to date Income Tax Clearance Certificate.

(f) Updated/up to date Trade Licence.

(g) List of existing commitment & contracts under government organization.

(h) Declaration of necessary Manpower for implementation of works.

TDS/PDS--D. Tender Preparation--

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
OR
The prices quoted by the Tenderer shall be adjustable as follows:

Iif prices shall be adjustable, the methodology for adjustment should be specified]
 

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.

TDS/PDS--E. Tender e-Submission--

The deadline for lodgement of e-Tenders is [state time, and identify a.m or p.m, i.e 10.30 a.m]


[state date i,e. 15 june,2011 ].
 

The deadline for lodgement of e-Tenders is 29-July-2021 PM

TDS/PDS--G. Contract Award--

The amount of Performance Security shall be [state percentage] percent of the Contract Price.

[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ]
 

The amount of Performance Security shall be 05 (Five) percent of the Contract Price.

Brief Description of Goods,Works or Service

At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

At Kamalapur Railway station Dhaka: Raising of platform no. 06 & 07 for the facilities of passenger as per drawing.

Amendment / Corrigendum/ Addendum No. : 1
S. No. File Name File Description File Size
(in KB)
1 Section-7.doc General Specifications 131042
2 Section-8.doc Particular Specifications 175182
3 Section-9.doc Drawing 128238
 
Save As PDF